Background Image
Previous Page  23 / 72 Next Page
Information
Show Menu
Previous Page 23 / 72 Next Page
Page Background

COVER STORY

August 2015

MODERN MINING

21

Michaël Fourie, SPH project manager at

Pilanesberg Platinum Mines, has been on site

since 2011 and has seen a steady ramp up in

their earthmoving and allied machine fleet to

keep pace with increasing mine throughput.

Rising production has also led to a progressive

up-sizing of the capacities on individual earth-

moving units.

At the ROM stockpile, SPH’s Cat fleet of

hydraulic excavators and wheel loaders works

in conjunction with three Metso Mobile LT120

jaw crushers. All blasted in-pit material is

transported to a ROM stockpile area by a sepa-

rate load and haul contractor. A total of around

300 000 tonnes of ore (Merensky Footwall

Pseudo Reef (Silicate) and UG2) is processed

and hauled for the client, Pilanesberg Platinum

Mines, on average per month.

“Two thirds of our tonnage is Silicate ore,”

Fourie explains. Allied materials handling

chiefly comprises UG2 reef. These are relatively

high Specific Gravity (SG) materials. With

these SGs all machines work physically hard

and need to be optimally configured for their

assigned tasks to ensure predicted availability

Above:

The Cat 340D2 L is

manufactured at Caterpil-

lar’s Xuzhou factory in China

for worldwide distribution.

Above left:

In the fore-

ground, a Cat 320D L hy-

draulic excavator, equipped

with a hydraulic hammer,

breaks up oversize material,

which will then be fed into

one of SPH’s Metso LT120

mobile jaw crushers.

goals are met, and scheduled maintenance

stays within budget.

SPH deploys a Cat 980H wheel loader to

handle any oversize. Cat 320D L excavators

equipped with hydraulic hammers then break

up larger ‘boulders’ for subsequent feeding into

the Metso Mobile jaw crushers.

Cat 966H units are utilised for general pre-

and post-crushed materials handling stockpile

management. The Cat 980H has recorded close

to 22 000 hours from new since being on site

with only minor interventions, and SPH plans

to run the machine to 25 000 hours before

reviewing component rebuild requirements.

Meanwhile, SPH’s Cat 966H units on site

have each achieved around 12 000 hours; a new

Cat 966H joined the fleet in July 2015 bringing

the total to four. The new unit comes equipped

with a larger counterweight and a 4 m³ bucket.

On the critical path to the crusher, mate-

rial loading is carried out by 40 and 50 tonne

class hydraulic excavators. These include a Cat

340D L, which is one of the key loading tools,

and comfortably keeps pace with the LT120’s

volume throughput. This typically averages