Background Image
Previous Page  33 / 72 Next Page
Information
Show Menu
Previous Page 33 / 72 Next Page
Page Background

August 2015

MODERN MINING

31

NIOBIUM

is the current size of Magris Resources’ Niobec

operation in Canada, thus allowing useful com-

parative analysis.

With the success achieved in the PFS in

both mill feed grade and metallurgical recover-

ies, the initial ferroniobium production from a

2 Mt/a plant now approximates to 8 to 10 % of

world production. For this reason, and to sim-

plify financing arrangements, the FS has been

scoped so as to achieve a more modest entry

into the market (i.e. throughput commencing

at 1,3 Mt/a). The FS will allow for expansion

of production as demand grows. The base case

examined in the PFS estimated an initial capi-

tal expenditure of US$158 million but a staged

approach will reduce this figure to US$123

million.

The FS is on track for completion in the

fourth quarter of 2015 with key milestones

including: the finalisation of the geotechnical

drilling campaign for the plant foundations

and tailings facility area completed in June

2015; the export of geotechnical samples to

Johannesburg, with two of the three batches

already at the laboratory and test work having

started; and finalisation of the mineral resource

model for use in pit optimisations.

On the metallurgical side, mini pilot plant

tests on approximately 5 tonnes of RC chips

have been completed at SGS Lakefield in

Canada with the preliminary results confirm-

ing the robustness of the PFS flowsheet. SGS

is now following up with larger-scale tests in

a 75-t integrated pilot plant that was entering

operation as this article was being prepared.

The mining licence renewal documents

have been submitted to the Tanzanian Ministry

of Energy and Minerals and the ESIA docu-

mentation has been submitted to the National

Environmental Management Council. These

authorisations are expected to be completed in

the third quarter of this year.

Offtake discussions with traders and end-

users are progressing well, says Cradle. The

discussions are focused on optimising pricing

and volume and both end-users and traders in

the USA, Europe and Asia are being targeted.

Two rigs were mobilised to site in June 2015

for drilling of geotechnical and hydrological

holes. One rig was dedicated to drilling the 13

geotechnical diamond holes (typically <25 m

deep) to enable characterisation of the ground

beneath the proposed process plant and tailings

facility; this work has now been completed.

The other rig is focused on drilling hydrologi-

cal observation holes in the area surrounding

the proposed Tailings Storage Facility (TSF).

Consultants from SLR Consulting (Africa) and

SRK Consulting (Australasia) have been on site

to supervise the logging and preparation of

these samples.

“The Feasibility Study is progressing as

planned with a processing plant throughput of

1,3 Mt/a being selected for initial production

expanding to 2,6 Mt/a after five years,” says

Cradle’s MD, Grant Davey, commenting on the

progress of the project. “Preliminary financial

results calculated for a staged throughput sce-

nario continue to highlight that Panda Hill is

a world class mineral resource project. We are

actively collecting all the necessary field infor-

mation as well as preparing for the 75-tonne

pilot plant test so that we have all the techni-

cal information to complete the final Feasibility

Study. The appointment of Dennis Cooke is

instrumental in ensuring that the construction

and operational team is appointed and have

ownership of the Feasibility Study. Offtake

negotiations are progressing well and all licens-

ing approval applications have been submitted

to the government for assessment. The Cradle

team is focused on ensuring that Panda Hill is

the next world class niobium producer.”

Photos courtesy of Cradle Resources

View of Panda Hill. It is

located just 26 km from

the major regional centre

of Mbeya in south-western

Tanzania.

The base case

examined in the

PFS estimated

an initial capital

expenditure of

US$158 million

but a staged

approach will

reduce this figure

to US$123 million.