The EPC supplied documentation for installation, commissioning and

site acceptance testing (SAT) not used.

Full installation quality control, testing and commissioning dossier not

available. Such as:

Documentation available was sparse and did not provide sufficient evidence of

testing of all installed equipment;

No installation quality assurance inspection certificates;

Some continuity and earth test certificates for the instrument cable not dated:

No continuity and earth test certificates for the power cable:

No as-built drawings (e.g. red lined or as-built available on site).

The level voting was 1oo2 sensors, but the level trip settings on each

sensor was different and at wrong settings.

There were calibration issues for the new radar level sensors, with

different ranges and zero datum points used for same tank.

Findings