Background Image
Previous Page  59 / 68 Next Page
Basic version Information
Show Menu
Previous Page 59 / 68 Next Page
Page Background

Wire & Cable ASIA – September/October 2007

57

Wire & Cable ASIA – November/Decem 11

In order to route vertical cables efficiently and

unobtrusively inside buildings, Corning’s design efforts for

this product focused on smaller diameter and more flexible

units leading to FRNC micromodule cables as shown in

Figure 3

.

An additional advantage of this cable is the extremely

small bend enabled by ClearCurve

®

[2]

fibre that allows

discreet storage of fibre in the building, either for tether or

for excess pigtails lengths.

The flexibility and the small outer dimensions of the riser

cable assembly ensure the very easy installation of the

cable and routing through the wall or on the various levels

of the building.

2 Installation conditions

One of the most critical issues

related to cable installation is

pulling through the vertical duct

already installed in MDUs (

Figure 2

).

The following tests were performed

to simulate installation conditions

and define installation limits

of the cables in terms of duct

congestion. The installation pro-

cess was simulated for several

duct diameters and shapes both

with and without copper cables

already installed. Additionally, duct

misalignment and gap size shown

in

Figure 4

were considered.

Tests were performed for 3m duct

pipes with different dimensions.

This simulates typical 3m distances between floors in the

MDU building.

Each cable was pulled three times for every configuration.

Figure 5

shows the pulling force for a 6x4 configuration

measured for three duct with various inner diameters (ID)

and with different filling ratios.

Results showed that the most important factor is

the number of riser tap points, which will be pulled

simultaneously through the duct. However, the pulling

force for different fill ratios depends also on copper

twisted pairs arranged inside the duct.

The total pulling force during installation should not exceed

500N. Based on duct size, fill ratio and misalignment data,

the maximum number of tap points pulled simultaneously

can be calculated as:

Where, F# is number of floors, MF is misalignment force

and PF is pulling force.

3 Reliability

The qualification test plan was a variation of the GR-3122

specification, modified to reflect indoor usage.

Test samples were prepared in the most common

configurations; 6 x 4 – 6 tap points, each with 4f, 12 x 4

– 12 tap points, each with 4f and 12 x 8 – 12 tap points,

each with 8f.

For such a set of samples the following tests were

performed: thermal aging, thermal and humidity cycling,

sheath retention, cable flexing, compression, assembly

installation, pulling through ducts, cable pulling and

straight and 90° tether pull. All tested samples passed

both environmental and mechanical tests without any

issues.

As an example for the extensive test programme the

sheath retention test set-up is presented in

Figure 6

.

Figure 6

:

Sheath retention setup

Electronics

35%

Passive

components

15%

Labour

50%

Max. # of tap points

Mandrel

15x

cable

diameter

Basket

grip

Cable held

firmly in

place

To optical

test equipment

Cable

Load

Over-

mold

Figure 7

:

Typical first installed cost

[3]