Background Image
Previous Page  60 / 68 Next Page
Basic version Information
Show Menu
Previous Page 60 / 68 Next Page
Page Background

Wire & Cable ASIA – September/October 2007

58

Nove ber/De ember 2 11

Test condition

:

The entire test was performed using typical indoor

temperature cycles and an applied force of 500N (50kg).

Two access jumpers were connected to the sample

during the test. Optical monitoring of insertion loss was

carried out both before and after the test.

All samples were put inside a walk-in chamber with two

access jumpers on both ends. Samples were conditioned

for 1h at each temperature and tested for 15 minutes.

System measurements were taken before and after

test exposure.

4 Deployment cost

Estimations of typical first-installation costs of fibre to the

home networks is shown in

Figure 7

.

Labour typically represents half of the first installed costs

of fibre to the home networks while passive components

represent only 20% of the total investment.

There are two elements concerning the labour costs,

namely the time to deploy, test and troubleshoot, and the

hourly rate of the installer required to install the network.

That hourly rate depends on the skill set and equipment

required to install the components.

Major MDU architectures used for MDU deployments are

shown in

Figure 8

:

a) traditional point to point solution – all fibres are

individually terminated at the

customer side

b) blowing fibres – individual fibres/

cables blown from basement to the

customer

c) mid-span access – cable sheath

is cut and fibres are selected and

extracted on each floor

d) pre-connectorised riser – 100%

factory tested ‘plug and play’

solution

The approach of a point-to-point as

well as of blowing fibre has been to

run individual fibre cables from a single

point in the basement to each floor

of a building, because of the need to

centralise splitters or electronics.

Both these approaches result in

significant labour time and a high level

of craftsmanship of the skilled splice

technician who covers the feeder and

distribution segments of the network

being needed.

Even more for mid-span solutions,

where the cable sheath needs to

be cut and individual fibres are

selected and extracted on each floor,

highly skilled installers are required

and significant constraints in the

deployment time appear.

Additionally, owners of MDUs are

sometimes reluctant to grant approval

for a service provider to install new cabling and hardware

within their buildings, due to the disruptions these

activities will cause for their tenants – making the speed of

deployment even more important.

Table 1

shows a comparison of major MDU architectures

used for MDUs in terms of system characteristics.

The proposed riser cable can be quickly and easily

deployed with minimal disruption of the end customer.

Instead of traditional deployment techniques involving

a separate cable for each floor or the need to perform

a mid-span access at specified locations, the OptiRise™

is simply pulled through the vertical riser conduit.

The network access points then line up with the openings

in the riser conduit where the riser tethers can be

accessed.

The benefits of this innovative approach enable

considerable advantages in the speed of deployment,

while significantly decreasing the number of skilled

installers needed to complete an installation successfully.

At the same time, the risk of reworks and failures is

reduced due to each fibre in the riser cable being 100%

factory tested before shipping to the customer and

provides valuable test points during deployment and for

later trouble shooting.

A pre-connectorised solution reduces health and safety

risks associated with fibre cable preparation and splicing.

a) Point to point solution

b) Blowing solution

c) Midspan solution

d) Proposed preconnectorised riser cable

Figure 8

:

Major FTTH architectures used in MDUs