Previous Page  31 / 52 Next Page
Information
Show Menu
Previous Page 31 / 52 Next Page
Page Background

TRANSFORMERS + SUBSTATIONS

“And the knock on savings were outrageous. We

closed a site with running costs of R150 M per

month five months early. As a result, 1,4-million

tons of ore were put through the mine before it

was due to open – and the capital expenditure

for the development of Kolomela, which was

about R8,4 billion, was paid off in 24 months,”

Jackson reveals.

From electrical to mechanical plant?

Pit dewatering at Kolomela is achieved via

16 boreholes that lower the surrounding water

table. “The water is fed into an eight-million litre

water tank and it is then pumped 18 km as pota-

ble water to Beeshoek, into the Vaal Gamagara

municipal intake at up to 1 500 m

3

/h.

“While the mine had moved towards offsite

modular designs with respect to its substations

and MCCs, the pump house itself experienced

civil delays. We had a fully functional MCC

control room and all of the medium-voltage

infrastructure onsite and operational, but the

pump station building hadn’t been completed.

So, while massively successful on the electrical

side, we were still being hampered by delays

on the civil andmechanical side,” Jackson says,

adding, “the budget for the pump station build-

ing was originally in the order of R1,8 M, but it

ended up costing well north of R4 M – and it

was more than eight months late.”

“Onsite construction of plant at remote

mines is such an onerous thing. A project can

be hampered by continuous delays, due to late

deliveries of inputs, the wrong people being

sent to site and a host of safety and security

restrictions that make rapid progress impos-

sible,” he explains.

Have there been similar projects?

Following the success of Kolomela on the

electrical side, therefore, when another pump

station project emerged, Jackson, with Kevin

Hundley who was with Aurecon at that time,

began to explore a similar approach. Themining

pit at Sishen, which is one of the largest open cast

pits in the world, is becoming deeper, so an ad-

I n C o n v e r s a t i o n W i t h

Our innovative, custom-built mega substations, pump stations, bunded transformer bays and more redefine “completely tested and commissioned offsite modular solutions”. 90% reduction of challenging site related work with massive project savings. BEE level II (new code) ISO 9001:2008 +27 11 928 4800 rfq@efficient.co.za www.efficientpowersa.co.za