Previous Page  54 / 90 Next Page
Information
Show Menu
Previous Page 54 / 90 Next Page
Page Background

2 15

BEST

PR

O

JECTS

50

CONSTRUCTION WORLD

DECEMBER

2015

Specialist Contractors or Suppliers

B

Project information

• Company entering: Aveng Grinaker-LTA

• Project start date: 28 May 2014

• Project end date: 28 February 2016

• Client: Sasol Synfuels

• Main contractor: Aveng Grinaker-LTA

• Project manager: Aveng Grinaker-LTA

• Consulting engineer: Wynand Louw

& Associates

• Project value: R66 037 396,82

Repeat client, Sasol Group Technolo-

gies, required urgent repairs to their

eight rapidly dilapidating concrete

process water cooling water towers.

The scope would entail the removal of

spalled concrete, replacing of reinforcing,

reinstating with structural grout and sealing

of the entire structure with polyurethane

coatings. Sasol engaged the services of

Sasol Process Water

Cooling Tower

Aveng Grinaker-LTA’s specialist concrete

repairs team to carry out the repairs to the

first tower in need of the most repairs, with

the possibility of more towers being awarded

at a later stage.

Providing safe access to the top of the

tower and work face provided the most

complicate challenge – especially with the

complex shape of the structure. The Process

Water Cooling Towers at Sasol Secunda are

140 m high, 65 m in diameter at the top and

105 m at the bottom.

The structural raking columns take up

the bottom 20 m and prop up the structure.

Access is provided by a means of Alimak and

24 Temporary Suspended Platforms. These

comprise of 16 x 8 m wide working platforms

and 8 x 4 m wide shuttle platforms. Alimak is

installed to the profile of the Process Water

Cooling Tower.

The vertical level was controlled with

a theodolite. Mast sections were running

parallel to the tower surface and anchored

to the concrete. Initially the anchors were

chemical anchors which changed over to

express anchors due to the 150 mm thick-

ness of the wall. The profile against the

tower was achieved by installing spacers

to the mast sections to allow the sections

to curve. This is only done every second

section. Special brackets were designed to

accommodate the walking platform on the

top rim of the cooling tower.

A monorail section is installed with

brackets to allow a temporary platform to

suspend from the brackets while still being

able to transverse horizontally. The move-

ments (vertically as well as horizontally) of

the temporary suspended platforms (TSPs)

were the main concern of the project as this

is where the most time would be lost.

As the project kicked off into the

construction phase, extra methods were

adopted and innovated to achieve a higher

efficiency. These included a trap door design

to allow the team to enter from the top

platform to reduce the lost time of access

to the system. This eliminated the time lost

by using the shuttle platforms to access the

work area from ground level.

Special

Mention