Previous Page  58 / 90 Next Page
Information
Show Menu
Previous Page 58 / 90 Next Page
Page Background

2 15

BEST

PR

O

JECTS

54

CONSTRUCTION WORLD

DECEMBER

2015

Specialist Contractors or Suppliers

B

Introduced into the South African

market by Kaytech, the Tensar

TW1 System was developed as an

alternative to traditional retaining wall

options and has been used extensively

in Europe and elsewhere internationally.

The system was recently used on a major

road upgrade contract in Ballito, one of the

first and largest local applications of the

system to date.

Project engineers, SMEC South Africa,

were involved in the detailed design of

the system and realised a number of cost

benefits on the project by using the Tensar

TW1 System.

The scope of works entailed the

widening of a two-lane, single carriageway

to a three-lane, dual carriageway in Ballito,

about 40 km north east of Durban. Due to

the site’s undulating topography, earth-re-

taining structures had to be built to bring the

extra lanes to level. The lane widening had

to be constructed within the road reserve to

eliminate encroachment into existing devel-

opments. To reach this objective, two near

vertical, Mechanically Stabilised Earth (MSE)

walls of 11 m and 5 m, covering a total length

of over 400 m and 2 000 m

2

, were proposed.

A key consideration in the design was

to optimise the use of lower quality fill

material, while simultaneously minimising

the amount of lateral support required in

cutting back and benching into the existing

roadway; i.e. the back excavation slope.

Limited space was available for the 11 m

high wall, which restricted the length of the

strips to 7 m. At the same time it would be

beneficial to the project if Berea sands could

be utilised. However, by using the lower

quality fill, strip lengths would need to be

increased, which implied either increased

cut or the use of a near vertical back excava-

tion slope requiring the use of shotcrete and

ground anchors or nails.

After a number of iterations, the final

design for the 11 m high wall comprised the

use of 7 m long strips, a granular backfill for

most of the height and 1 m thick granular

soil-raft foundation. No lateral support was

thus required and conventional benching

Kaytech SystemUsed in Major Ballito Road Upgrade

Project information

• Company entering: Kaytech

• Project start date: June 2013

• Project end date: September 2014

• Client: Kwadukuza Municipality

• Project team: Kaytech, SMEC and Afriscan

• Main contractor: Afriscan Construction

• Project manager: SMEC South Africa

• Project value: R8,5-million (walls and fills)

into the existing fill was utilised. For the

upper 3 m of the 11 m wall and for the 5 m

high wall, Berea sand was used throughout.

In utilising the new system a number

of challenges were experienced during

construction. These included: the setting

of the base block, which is key to achieving

the final face inclination of 86°, compac-

tion criteria, stormwater control, and the

use of labour inexperienced in building

these walls. However, these problems

were quickly resolved through close collab-

oration between the contractor, consultant

and supplier.

From the Environmental Assessment

it was noted that the removal of existing

indigenous trees within the road reserve

would result in a loss of biodiversity. This

however was unavoidable due to the nature

of development. Rehabilitation measures

had to include replanting the same species

of trees. Also during construction large

amounts of soil disturbances are expected.

Re-vegetation of all disturbed soil was insti-

tuted immediately after construction.

As another environmental advantage,

the TensarTech TW1 system (MSEW) is ideal

as an alternative to traditional retaining wall

options as the geogrid and geotextiles used

in its construction assist in reducing the

project carbon footprint, and at the same

time minimise the use of natural materials.