Previous Page  56 / 90 Next Page
Information
Show Menu
Previous Page 56 / 90 Next Page
Page Background

2 15

BEST

PR

O

JECTS

52

CONSTRUCTION WORLD

DECEMBER

2015

Specialist Contractors or Suppliers

B

With the University of Pretoria contin-

uing to grow and more and more

students coming from outside

Pretoria, student accommodation is

very scarce. Ellinas Developers saw an

opportunity here and successfully leased

the planned ‘Hatfield Studios’ to the Univer-

sity and a very ambitious build commenced

in November 2013, occupation date

December 2014.

Project information

• Name of company entering: PERI Formwork

& Scaffolding Engineering

• Project start date: 8 July 2013

• Project end date: December 2014

• Client: Feenstra Group

• Project team: Feenstra Group

• Main contractor: Basil Read

• Architect: Boogertman + Partners

• Project manager: Feenstra Group

• Quantity surveyor: DelQS

• Consulting engineer: DG Consulting

Engineers

Hatfield Studios

Generally a building will have two to

three shafts for access, one for lift access,

and one or two for stair/emergency exit.

Hatfield Studios which consisted of a large

parking basement and two towers of rooms,

had a grand total of 12 shafts.

Inaddition to this, the east andwestwalls

of the basement and towers were off-shutter

concrete feature walls. The progress of a

shaft or feature wall always determines the

progress of the whole project.

Cranage was always going to be a

critical resource and with the construc-

tion site having a relatively small footprint,

the main contractor decided on only two

tower cranes.

With each shaft and feature wall

requiring at least four hours of crane time, 56

crane hours would be consumed every two

weeks on the shafts and feature walls alone

to meet the ambitious programme.

Also, the towers were designed with

structural internal walls requiring crane

lifting of gang-formed shutters there too.

The advantage of this design is that

the floors are very modular which is perfect

for custom made table formwork.

The initial plan from the formwork

supplier was to utilise 16 m

2

tables and crane

them into position, one by one.

It soon became apparent that there

would not be sufficient surplus crane

capacity to move flooring formwork.

The tables were replaced with the light

man-handable Skydeck 1,125 m

2

panel

which could be carried from floor to floor.

The heaviest part of the Skydeck system, the

2,25 m long main beam, weighs just 15,5 kg.

Eight hour days quickly turned into

16 hour days with self-compacting concrete

being poured late into the night. Although it

was a very ambitious programme, accuracy

was paramount as the main contractor had

opted for a pre-manufactured modular bath-

room requiring tolerances of millimeters to

fit into the rooms.

Errors did occur and critical remedial

work had to take place including breaking

down an interior wall, propping the floors

and then recasting the walls from the bottom

of the shutters with self levelling concrete

and a special pump/shutter adaptor.

Labour took strain with the long

hours, there was a month-long steel strike

during winter, but the University took

reasonable occupation in the middle of

December 2014.

Photos by Oliver Karstel