TAR NC Implementation Document – Second Edition September 2017
The consultation document for the final consultation must include information listed
in Table 12. The section below describes the difference between the ‘final’ and the
‘intermediate’ consultations.
CONTENT OF THE FINAL CONSULTATION DOCUMENT UNDER ARTICLE 26(1)
Article 26 (1)
Content of consultation
Comparison with Articles 29 and 30
(a) Proposed RPM
Assumptions and justification for parameters used in
the proposed RPM per Article 30(1)(a)
Article 30(1)(a): examples are provided,
‘justification’
is not covered
Proposed adjustments for points with storage,
LNG facilities and infrastructure ending isolation of
a MS per Article 9
Article 30(1)(c)(iii): part of the
‘reference prices and
other prices applicable at points other than where the
CAM NC applies’
Indicative reference prices
Article 29: reserve prices at points where the
CAM NC applies
Article 30(1)(c)(iii): part of
‘reference prices at points
other than where the CAM NC applies’
Results, components and their details for CAA
per Article 5
Article 30(1)(v)(3): partially covered by
‘intra-system/cross-system split’
Assessment of the RPM
Not covered
Comparison of RPM to the CWD in Article 8
Not covered
(b) Revenue and
splits
Indicative allowed and / or target revenue
Article 30(1)(b)(i): allowed and/or target revenue
Indicative transmission services revenue
Article 30(1)(b)(iv): transmission services revenue
Indicative splits of capacity-commodity revenues,
entry-exit revenues, intra-system/cross-system
revenues
Article 30(1)(b)(v): splits of capacity-commodity
revenues, entry-exit revenues, intra-system /
cross-system revenues
(c) Commodity-
based and
non-transmis-
sion tariffs
Manner in which they are set
Article 30(1)(c): covered by
‘relevant information
related to their [tariffs] derivation’
Share of the allowed or target revenue to be
recovered by these tariffs
Article 30(1)(b)(v)(1): covered by
‘capacity-commodi-
ty split’
for commodity-based transmission tariffs
Article 30(1)(b)(i) and (iv): covered by
‘allowed
and / or target revenue’
and ‘
transmission services rev-
enue’
for non-transmission tariffs
For non-transmission tariffs, manner of revenue
reconciliation
Not covered
Indicative tariffs
Article 30(1)(c)(i): commodity-based transmission
tariffs
Article 30(1)(c)(ii): non-transmission tariffs
(d) Changes in
transmission
tariffs
Changes in tariffs for comparable services from the
prevailing tariff period to the tariff period for which
information is published – indicative comparison
between: (1) prevailing tariffs at the time when the
consultation document is published; and (2) indicative
tariffs based on the proposed RPM
Article 30(2)(a)(i)
Changes in tariffs for comparable services from the tar-
iff period for which information in published to each
subsequent tariff period until the end of the prevailing
regulatory period – indicative forecast based on the
proposed RPM
Article 30(2)(a)(ii)
At least a simplified tariff model to calculate tariffs
and estimate a possible future evolution
Article 30(2)(b)
(e) Fixed
payable price
approach
Proposed index
Not covered
Risk premium: calculation and proposed use
Not covered
Where and when such approach is proposed
Not covered
Process for offering capacity at IPs where both fixed
and floating price approaches are offered
Not covered
Table 12:
Content of the final consultation document under Article 26(1)