Article 29 and Article 30 have a certain degree of overlap with respect to the

publication requirements and the content of the final consultation document. Table

12 compares Article 26 to Articles 29 and 30 together. The information included in

the final consultation document is only indicative, and is relevant for a given period-

ic consultation conducted at least every five years as from 31 May 2019 which is the

deadline for the NRA decision on the first consultation. In contrast, the information

for publication before the annual yearly capacity auctions, and before the tariff

period, is binding and relevant for a given gas year or tariff period. Effectively, almost

all the information included in the final consultation document subsequently

‘converts’ into binding information for publication before the annual yearly capacity

auctions and before the tariff period. The latter information also includes other

information not mentioned in Article 26. An example is the reserve prices, including

multipliers, seasonal factors, interruptible discounts, which are subject to

consultation every tariff period under Article 28, and not to periodic consultation

under Article 26.