Previous Page  36 / 72 Next Page
Information
Show Menu
Previous Page 36 / 72 Next Page
Page Background

34

CONSTRUCTION WORLD

APRIL

2016

PROJECTS AND CONTRACTS

The Nojoli project comprises 44 Vestas V100 2 MW wind

turbine generators, which have the capacity to generate

more than 275 GWh per year or enough for 86 000 South

African households.

“In recent years we have transported and erected over 160 turbines

at wind farms around South Africa,” said project and mechanical engi-

neer, Robbie Boshoff.

The company’s contract commenced with discharging the vessel in

December 2015 at the Port of Ngqura near Port Elizabeth, and storage at

the port. “The team on this tight-deadline project had an early start to

the year, arriving back to discharge a second vessel on 2 January 2016

with further vessels to be discharged throughout the project.”

According to Boshoff, the contract will run until 23 June 2016, and

WIND TURBINES

at

NOJOLI

Locally based international heavy-lift,

specialised transport and plant installation

company, Vanguard has been awarded the

transport and crane erection contract for

the Nojoli Wind Farm near Cookhouse in the

Eastern Cape, once again showcasing its

experience in this sector and its specialised

engineering solutions.

>

involves not only the discharge and storage at the port, but also special-

ised transportation of all components to site, about three and a half

hours away, followed by the erection of the turbines utilising Vanguard’s

GTK1100 crane.

A fleet of extendable and multi-axle trailers transports the compo-

nents, which include nacelles weighing 72 tonnes, hubs of 21 tonnes,

and turbine blades of 50 metres in length.

“Among the challenges to be managed on this route to site is a

mountain pass with very narrow turns,” said Boshoff. “We work with the

traffic authorities to close off the pass entirely, so that our extendable

trailers can safely use the whole road to manoeuvre the blades through

the turns.”

On site, the GTK crane is assisted by a dedicated and specialised

team, including two qualified Red Seal riggers, who lead the team

to assemble and break down the crane, so that it can be moved and

positioned for the next turbine – each process taking around 10 hours.

“Another team pre-populates the handstands with the components in

advance to ensure that no delays occur with the main build,” he said.

With every aspect of the job, detailed method and risk assessments

are done, including environmental assessments.

Once operational, Nojoli Wind Farm’s environmentally-friendly

electricity supply will save the atmosphere from more than 251 000

tonnes of carbon dioxide each year, which would have come from

coal-powered stations.

The wind farm is being constructed by Enel Green Power, which has

about 740 plants operating in 15 countries in Europe, the Americas and

Africa; EGP’s total installed capacity is 9 600 MW from a range of sources

including wind, solar, hydroelectric, geothermal and biomass.

Vanguard discharging the vessel and storage at the Port of Ngqura.

Vanguard GTK Crane is assisted by a dedicated and specialised team.