Background Image
Previous Page  101 / 140 Next Page
Basic version Information
Show Menu
Previous Page 101 / 140 Next Page
Page Background

C

oating,

J

acketing & Galvanizing Technology

99

J

anuary

2008

www.read-tpt.com

The work involved was

especially

complex

as

welding can cause material

shrinkage and distortion.

Because the overlay cladding

process requires vessels

to go through two welding

cycles, there were risks that

needed to be assessed and

addressed.

The Arc Energy welding and

fabrication teams therefore

needed to take considerable

care, both with the initial

setup and the welding

sequences, to ensure that allowances

were made for distortion. It was essential

that the customer received the vessel to

the exact specification ordered.

A second contract won by Arc involved

cladding four very large elbows as part of a

bigger project for Langfields Ltd, one of the

UK’s leading component fabricators. The

project at Shell’s Stanlow Refinery required

overlaying four 36" carbon steel elbows

with stainless steel.

Shell’s senior welding engineer, Mr Wayne

Griffiths, states

“The technical skills

and knowledge of welding procedures

required were so demanding that not many

companies can, or even want to, handle

this type of work. Arc Energy Resources

were able to ship the elbows to their

factory in Gloucestershire for weld overlay

cladding.”

Elbows are always difficult to handle

but to accommodate the unusually large

diameters for this project Arc Energy also

needed to design and build two special

jigs.

To meet the tight delivery schedule both

workstations operated 24 hours a day for

the duration of the contract. In addition,

Arc Energy was responsible for proving

the quality of its cladding prior to delivery,

by 100 per cent non-destructive testing.

Arc Energy’s third big contract involved the

corrosion-proof cladding of an 8.65m-long,

16" diameter superduplex riser for Mardale,

a leading supplier of pipeline packages for

the oil and gas industries.

The pipe is destined for a sour oil reservoir

located approximately 10km offshore

in the Gulf of Suez. Oil and gas from

the field will initially be produced from a

single, unmanned nine-slot platform with

a 16" multiphase pipeline. The riser is a

vital component, connecting with onshore

facilities.

Because media temperatures of 120ºC in

the splash zone create a very corrosive

environment, the project required Arc

Energy to fully clad the riser externally

using 16 plates of 3mm alloy 59. The

new procedures had to be qualified in

accordance with ASME IX and other

international standards. The test welds

and subsequent mechanical testing was

witnessed by independent inspectors.

Following completion of the seal welding,

the cladding was subjected to 100 per

cent DPI followed by a pressure test

using an inert gas at a pressure of 1 bar.

The pressure test was held for 15 minutes

minimum and the sealing weld was visually

examined to ensure that no leaks were

evident.

Arc Energy Resources

– UK

Fax

: +44 1453 823623

Email

:

sales@arcenergy.co.uk

Website

:

www.arcenergy.co.uk