Previous Page  402 / 406 Next Page
Information
Show Menu
Previous Page 402 / 406 Next Page
Page Background

GAZETTE

JULY/AUGUST

1985

terminated on 12 November 1974 the

Defendants became trespassers. Because

the premises have not been a "tenement"

at the relevant time there is no question of

a new tenancy arising.

Per McCarthy J. (dissenting)

The true construction of the events that

occurred after 30 June 1974 was that the

Defendants held the premises as tenants

from month to month. No notice to quit

purporting to terminate such tenancy

having been served they were entitled to

retain possession against all people and

the claim in this action for recovery of

possession must be dismissed. The sum of

£ 1,500.00 is due as rent not as mesne rates

or mesne profits.

Irish Shell & B.P. Limited -v- John

Costello Limited - Supreme Court (per

O'Higgins CJ and Henchy J., McCarthy J.

dissenting), 21 December, 1984.

Joanne Sheehan

PLANNING

Local Government (Planning & Develop-

ment) Acts 1963-1982 — Planning Appeal

— Rights of Third Parties.

The Hibernian Shirt Company & R.E.

Flanagan applied to Dublin Corporation

for planning permission for a shop/office

development at Great Strand Street and

Liffey Street, Dublin. The application

was refused by Dublin Corporation but

on appeal to An Bord Pleanala outline

permission was granted. There was no

oral hearing of the appeal and Dublin

Corporation appeared to have been the

only party to make direct representations

to the Bord in connection with the appeal.

The site in question is situate within an

area that had been earmarked by Coras

Iompair Eireann for development as part

of a projected Dublin Transportation

Centre. C.I.E. had made some indirect

representations to the Bord through the

planning department of Dublin Corpora-

tion but was not a party to the appeal.

Part of the Bord's reasons for allowing

the appeal were:—

"While the site is within an area which

may be affected by C.I.E. proposals

for Dublin Transportation Centre the

Bord is not satisfied that it is an

essential part of the land required for

such a centre and having regard to the

status of the relevant C.I.E. proposal

it is not considered that a refusal of

outline permission for the proposed

development would be warranted by

reference to those proposals."

C.I.E. obtained a conditional order of

certiorari

quashing the order of the Bord

but the cause shown by the Bord was

allowed and the order discharged by the

High Court. C.I.E. appealed to the

Supreme Court against the discharge.

The Court noted that C.I.E. had in

1976 adopted a proposal for a Dublin

Transportation Centre which would be

sited on each side of the Liffey between

O'Connell Street and Capel Street and

connected by a tunnel under the Liffey.

C.I.E. proceeded to acquire many

properties in the area designated and

Dublin Corporation as planning

authority gave recognition to the C.I.E.

proposal in its Dublin 1980 Development

Plan which stated:—

"The Planning Authority notes that

Coras Iompair Eireann is considering

a proposal to establish centre city

transportation termini adjoining

Ormond Quay Lower and Wellington

Quay and generally over the stations

in the proposed Rapid Rail Transit

system and will co-operate in the

provision by C.I.E. of any such

termini required for more efficient

transport services."

In fact no application for development

within the designated areas which would

materially interfere with the implemen-

tation of C.I.E.'s proposal for the Dublin

Transportation Centre has been granted

by Dublin Corporation.

I was in conformity with that policy

that Dublin Corporation twice turned

down the developers' application for

planning permission in this case. Dublin

Corporaiton has no reason to expect that

in the appeal their policy of seeking to

give effect to the C.I.E. proposals would

be interfered with without hearing C.I.E.

but that is what happened. The Court

stated that it was a classical example of

departure from the rule of

audi alterem

partem.

The court noted that the failure

to observe natural justice was particularly

serious because the party affected was

C.I.E., which under Article 65 of the

Local Government (Planning & Develop-

ment) Regulations 1977 was designated

as a "public authority for the purposes of

Section 5 of the Local Government

(Planning & Development) Act 1976"

and accordingly there was a duty on the

Bord "so far as may in the opinion of the

Bord be necessary for the performance of

its functions" to keep itself informed of

"the policies and objections for the time

being" of C.I.E. In this case the Bord not

only breached a rule of natural justice but

also disregarded the spirit, if not the

letter, of the liaison which the statute

envisaged as operating between the Bord

and C.I.E. in a case such as this.

The Court allowed the appeal and

granted an absolute order of

certiorari

to

quash the order of the Bord.

The State (Coras Iompair Eireann) -v- An

Bord Pleanala - Supreme Court (per

Henchy J.). 12 December, 1984 -

unreported.

John F. Buckley

Copies of judgments in the above

cases are available on request from

the Society's Library. The photo-

copying rate is lOp per page.

xxxi