Previous Page  404 / 406 Next Page
Information
Show Menu
Previous Page 404 / 406 Next Page
Page Background

GAZETTE

JULY/AUGUST 1985

were formerly any restrictions on change ot

use or rights of alienation the Court held that

they did not form part of a letting agreement.-

The subsequent direction that the restriction

should be introduced into the new lease was

inconsistent with the terms of the original

Order made in March 1981.

The Court however agreed with the view

obviously taken by the Circuit Court Judge

that a modern letting would normally include

restrictions on change of user and alienation

without the lessors consent and believe that

had these matters been present in the minds

of the parties they would have readily been

disposed of in the manner sought to be

achieved by the later order.

In the circumstances as the Court believed

that omission to have these matters dealt with

in the original hearing was attributable to an

oversight on the part of both parties and as

the only way this could be achieved was by

way of an appeal to the High Court against so

much of the Order of 6 March 1981 as

directed that the new lease should be subject

to the terms and conditions of the previous

tenancy the Court extended the time for lodge-

ment of a notice of appeal against that part of

the Order of 6 March 1981 up to a date 18

days after the date of the Judgement.

Francea Hill & Ors

-v-

Kathleen

Mulcahy

The High Court (per O 'Hanion J.) 30 April,

1984 - unreported.

PLANNING

Validity of permission — inadequate des-

cription of lands in advertisement — challenge

may be made by any party affected by per-

mission — planning authority has no power

to grant permission based on invalid appli-

cation — planning authority need not be party.

The Respondent, the E.S.B., had sought

an injunction against the Appellant, Carmel

Gormley, permitting it to enter on her lands

and exercise the purported powers contained

in Section 53(5) of the Electricity Supply Act,

1927, as amended.

Mrs. Gormley resisted the application on

the grounds (1) that the section was uncon-

stitutional and (2) that the planning permis-

sion obtained by the E.S.B. for the erection

of an electricity transmission line on her lands

was invalid. Notwithstanding the success of

the constitutional plea*, the Court gave a

decision on the planning issue.

The E.S.B. advertised its intention to apply

for planning permission in the Irish Indep-

endent on 8.1.76 in the following terms:—

"County Wexford.

The Electricity Supply Board intends to apply

to Wexford County Council for permission

to erect that portion of the Great Island

Arklow 220 k.v. line which lies between the

townlands of Forthchester Lower and Bally-

kilty Upper, near Coolgreaney, Co. Wexford.

J. F. Williams, Secretary."

The length of the proposed transmission

line was over 40 miles and the townlands ref-

erred to were those at which, so far as

Wexford County was concerned, the trans-

mission line would commence and terminate.

Wexford County Council notified its

intention to grant permission for the erection

of a 220 k.v. transmission line from Great

Island, Campile to Forthchester Lower, Inch

on 10.2.76 The final permission was granted

on 24.3.76. At this time the lands and

premises owned and occupied by Mrs.

Gormley were owned and occupied by a Mr.

Corcoran. These lands were situate in the

townland of Skeamanagh or

Farmley,

Barony of Scarawalsh County of Wexford

and were purchased by Mrs. Gormley in

October 1977 without notice of the granting

of the planning permission or of any intention

by the E.S.B. to place portion of its trans-

mission line across the lands involved.

Mrs. Gormley contended that the newspaper

advertisement was inadequate and not in

accordance with the statutory regulations

governing the making of planning applications •

and therefore the purported decision was

invalid.

The regulations applicable at the time of

the application for and granting of the pur-

ported permission were those contained in

S.I. No. 221 of 1964. The relevant provisions

of thse permission regulations are, firstly,

Article 9(1) which provides that prior to

making a planning application, the applicant

shall publish notice of his intention either in a

newspaper circulating in the district in which

the relevant land is situate or by erecting on,

or affixing a notice to, the land; and secondly,

Article 9(4) (b) which requires the newspaper

notice to set out "the location of the land or

the address of the structure to which the

application relates (as may be appropriate)".

The E.S.B. contended Mrs. Gormley could

not now assert or rely on any such invalidity

even if it existed on three grounds:—

1) Since Mrs. Gormley was not the owner or

occupier of the lands at the time the permis-

sion was sought and obtained, she could not

have been affected by the inadequacy of the

advertisement (this was the basis on which the

High Court had rejected her challenge);

2) Her application to set aside the permission

was statute-barred;

3) She could not seek to impugn a permission

in proceedings to which the planning author-

ity was not party.

HELD:—

The townlands mentioned in the advertise-

ment merely indicated the area in which the

line commenced and left Co. Wexford. It

would not have notified an owner or occupier

of lands that the townland in which he

resided might be affected, let alone inform

him his actual property might be affected —

except insofar as might have applied to those

persons living in either of the two named

townlands. Evidence was given that other

planning authorities required at least a list of

the townlands through which an electric wire

would be erected. Compliance with such a

requirement would at least have given a reas-

onable indication of the probable route to be

taken by the line. The advertisement did not

therefore comply with the permission regul-

ations and, following its decision in

Crodaun

Homes Limited

-v-

Kildare County

Council

[1983] I.L.R.M. 1 the planning authority had

no power or jurisdiction to grant permission

in respect of that application, since Section 26

of the Local Government (Planning & Dev-

elopment) Act, 1963, confines the exercise of

that power to cases where application has

been made in accordance with the permission

regulations. In the

Crodaun Homes

case, the

Court decided that in order " to satisfy the

requirement of stating the location of the

land, both the letter and spirit of the regu-

lations require that the site on which it is pro-

posed that the development should take place

must be correctly and accurately so described

in relation to the district in which the land is

situate as to be readily and reasonably identi-

fiable."

Reversing the High Court decision, that a

challenge to the validity of a permission,

based on non-compliance with the permission

regulations, can properly be made by any

person who is affected by the permission

granted. It does not depend upon the person

making the challenge being able to show the

non-compliance directly affected him. If non-

compliance is established, the permission is

invalid by reason of a want of power or

jurisdiction on the part of the planning auth-

ority to exercise their right of granting or

refusing permission.

The statutory time limit affecting the chal-

lenge to a validity of a permission is con-

tained in Section 82(3) (a) of the 1963 Act.

This Section was interpolated by Section 42

of the 1976 Planning Act, which was brought

into operation by S.l No. 56 of 1977 on 15.3.77.

Following the Court's decision in

Pine Valley

-v-

Dublin County Council

[1982] I.L.R.M.

169, the Section does not apply to a challenge

now made to a permission granted in 1976.

If a developer seeks to rely upon a grant of

permission directly affecting the interest of a

member of the public, and if the permission

can be shown to have been made without

authority, there is no requirement of pro-

cedure or justice to prevent a member of the

public successfully challenging the validity of

the permission without the necessity of

joining the planning authority.

The Court did not express any view as to

whether the E.S.B. was exempt from the pro-

visions of the Planning Acts.

The Electricity

Supply Board

-v-

Carmel

Gormley — Supreme Court (per Finlay Jnem-

diss) 21 May, 1985 - unreported.

Sarah Cox

•This plea was the subject of a separate decision of the Court

given on 21 March 1985.

CONTRACT

Retenlion of Title — Section

36

of The Agri-

cultural Credit Act 1978 — Whether Clause

amounted to Bill of Sale of Slock within the

meaning of the 1978 Act.

The Plaintiff was appointed as Receiver

over Charles Dougherty & Co. Limited which

carried on the business of manufacture and

sale of animal feeding compounds. The

Defendant was a supplier to the Company of

various components used in the preparation

and manufacture of the feeding compound.

The product was supplied on credit and the

Contract for Sale contained a condition No. 9

as follows:-

" T he transfer of title to you of the goods as

detailed in this Contract shall not occur until

the invoice covering same has been paid in

full, and, accordingly, the goods wherever

situate shall be thereupon at your sole risk".

Section 36 of The Agricultural Credit Act

1978 provides as follows:-

(1) A Bill of Sale of Stock (whether including

or not including any other chattels) made

after the commencement of this Act shall,

notwithstanding anything contained in the

Bills of Sale (Ireland) Acts 1879 and 1883,

xxxiv