Background Image
Previous Page  49 / 68 Next Page
Information
Show Menu
Previous Page 49 / 68 Next Page
Page Background

June 2015

MODERN MINING

47

MINING IN AFRICA

feature

Machines belonging to

mining contractor PW

Ghana in action at the mine.

Asanko Gold announced

in November last year that

it had selected PW for the

Nkran pre-strip – Nkran

is the main pit at Obotan

– plus the first year of

mining operations. The

prestrip operations are well

underway with the first

ore having being already

intercepted and stockpiled.

Genser Energy Ghana to build Asanko power plant

Asanko Gold Inc announced in

early June the signing of a binding

Power Purchase Agreement (PPA)

with Genser Energy Ghana Limited

(Genser) for the supply of all the

power required for Phase 1 of the

Asanko Gold Mine. Genser is an es-

tablished independent power pro-

ducer and power plant operator in

Ghana that provides power to large

industrial and parastatal clients.

Under the agreement, Genser

will build and operate a 19,2 MW

liquid fuel power plant adjacent

to the mine site and supply 17 MW

of nominal power to Phase 1 on a

fixed-price, life-of-mine contract.

The initial contracted rates for the

first two years (2016 and 2017) are

slightly below the rates that were

published in the Phase 1 Definitive

Project Plan in November 2014. In

2018 and 2019 the contracted tar-

iffs decrease in each year providing

a benefit to the long term operat-

ing cost profile of the mine.

Permitting and construction of

the 19,2 MW plant will begin im-

mediately, with power expected

to be available in Q4 2015 in ad-

vance of commissioning Phase 1 in

early 2016.

million when compared to a standalone Esaase

plant and associated infrastructure. These sav-

ings include a shared and expanded tailings

storage facility (US$23 million), utilisation

of the current power supply line being con-

structed for Phase 1 (US$7 million), buildings

such as workshops and offices (US$7 million),

civils works and plant terraces (US$7 million)

and savings in construction accommodation

and facilities (US$9 million).

An industry standard, troughed overland

conveyor has been chosen as the ore trans-

port method with a low operating cost of

US$0,71 per tonne. The conveyor represents

the most optimal method when compared to

the various other options that were reviewed

including trucking, rail or piping. Although

the capital cost of the conveyor is significant,

this is more than offset by the other savings

that have been achieved, as well as its low

operating costs, providing a net capital saving

of US$17 million compared to the standalone

2013 PFS for Esaase.

The Phase 2 study will be advanced to a full

Definitive Feasibility Study (DFS), which will

also seek to optimise the mining operations by

more efficiently sequencing the six open pit

deposits into one integrated mining schedule,

as well as achieve process synergies and opti-

misations. The DFS will commence during the

current quarter, with an investment decision

planned for Q2 2016.

The US$270 million, Phase 2 expansion will

take approximately 18 months to build, with

production from Esaase targeted to come on

stream in Q1 2018. This timetable is predicated

on a positive investment decision from Asanko

Gold’s board in Q2 2016.

The Phase 1 processing plant is currently

around 50 % complete. It includes single stage

jaw crushing with reclaim from a live stockpile

and open circuit SAG mill, feeding cyclones

that in turn operate in a closed circuit with a

ball mill. A pebble crusher will receive scats

from the SAG mill, crush them and return

them to the SAG for further grinding. The

hydrocyclones will achieve the final product

size of P80 106 µm. A gravity circuit will be

utilised to treat a portion of the cyclone under-

flow stream to recover coarse free gold, around

40 %, from the recirculating load. The milled

product will gravitate to a trash screen before

entering a pre-leach thickener followed by a

conditioning tank.

A seven-stage CIL circuit will be used to

leach and adsorb gold from the milled ore onto

activated carbon. An AARL elution circuit will

be used to recover gold from loaded carbon.

Cyanide in the CIL tailings will be detoxified

using the SO

2

/air method.

The Phase 2 expansion project will expand

the central processing facility with the addi-

tion of a 5 Mt/a ball mill, gravity concentrator

followed by a flotation circuit. The concentrate

from the float circuit at a mass pull of plus/

minus 10 % will be reground and then trans-

ferred to a new CIL circuit for leaching and then

final gold production.

Phase 2 further makes provision for the

opportunity to optimise feed material streams

to either the flotation or whole ore leach circuit

via interlinking conveyors between the respec-

tive mill feed circuits. In doing this, there is an

opportunity to optimise recoveries and oper-

ating costs depending on the ore types being