Background Image
Previous Page  55 / 68 Next Page
Information
Show Menu
Previous Page 55 / 68 Next Page
Page Background

June 2015

MODERN MINING

53

MINING IN AFRICA

feature

Key results at US$1 200 per ounce

Units

Value

Ore

kt

25 474

Grade

g/t Au

2,80

Gold contained

koz

2 291

Gold produced

koz

1 901

Pre-production capital cost

US$M 74,1

Total cost

US$M 1 680

Key financial results

Units

Value

Cash cost per ounce produced (operating only)

US$/oz

789

Revenue

US$M 2 254

Net cash flow

US$M 441,5

Net present value (10,0 %)

US$M 189,4

Internal rate of return

%

42

Payback from start of development

years

3,8

TABLE 1:

Key operational and financial study results

process. However, the accuracy of assump-

tions is sufficient to meet the ±25 % accuracy

of a PFS and small changes in parameters are

unlikely to materially impact the production

schedule or cost model.

On the hangingwall side the cave draw angle

is expected to be about 65 deg while, on the

footwall side, failure of the footwall would not

extend beyond the footwall contact. The foot-

wall domain to the east of the Syama Shear

provides competent rock mass conditions

determined suitable for the mine infrastructure

(decline, vent raises, substations, sumps and

pump stations).

Decline development is expected to com-

mence in early calendar 2016 from within the

Stage 1 open pit from a portal located 200 m

below the surface. This will allow early access

to underground ore, for development of initial

production stopes, while work continues to

extend the decline to the surface for long-term

access to the underground.

Resolute has already commenced the project

work required for a DFS to facilitate an early

decision to commence underground mining.

The DFS is due for completion in the March

2016 quarter.

Commenting on the results of the revised

PFS, Resolute’s outgoing Chief Executive

Officer, Peter Sullivan, said: “Completion of

the updated PFS validates our confidence in

the underground development at Syama and

delivers a capital efficient outcome with strong

long-term cash flows until at least 2028. Our

activities over the past 12 months have sig-

nificantly boosted the Syama underground

reserves and established it as a robust and long-

life gold mine. Excitingly, the study has also

identified further project upside as the orebody

remains open at depth which, with additional

drilling, should lead to further resource and

reserve increases.”

Syama is located in the south of Mali,

approximately 30 km from the Côte d’Ivoire

border and 300 km south-east of the capital,

Bamako. During the 2014 financial year, the

plant treated 1,78 Mt at an overall head grade

of 3,73 g/t Au to produce 165 493 ounces of

gold at a cash cost of US$1 006 per ounce. An

oxide circuit to allow treatment of satellite

deposits at Syama was commissioned earlier

this year.

Apart from Syama and Ravenswood,

Resolute also owns the Bibiani gold mine in

Ghana. Bibiani was acquired last year and is

currently on care and maintenance but Resolute

is planning an underground operation at the

site. Resolute also used to operate the Golden

Pride gold mine in Tanzania. It is now mined

out, however, and was closed at the end of

2013, after having produced 2,2 Moz of gold

over a mine life of 15 years.

True Gold’s Karma site “buzzing with energy”

True Gold Mining Inc, listed on the

TSX‑V, reports that full construction of

its Karma gold project in Burkina Faso

has resumed after it was suspended –

due to community relations issues – ear-

lier this year.

“Construction activities and local

procurement have ramped up and we

are on schedule for first gold pour by the

end of Q1 2016,”says the company.“With

over 250 staff on site, we are underway

with excavation of the storm and raw

water ponds as well as site preparation

for the heap-leach pad.”

According to the company, a Kom-

atsu PC3000 excavator and four of six

Komatsu 785 trucks (100-t capacity)

have been commissioned, the assem-

bly of a Komatsu WA800 wheel loader

has started, while the hard rock crusher

(an MV 2000 VSI) has arrived on site. The

temporary fuel storage farm has been

completed, the construction of the main

haul road initiated and the ADR building

structural steel has been delivered.

“I am extremely pleased with the

speed and efficiency our team has dem-

onstrated in getting back to work since

mid-May,” comments Christian Milau,

True Gold’s CEO.

“Over the last few weeks we have

made significant progress towards first

gold pour. The site is buzzing with en-

ergy and the excitement of being back

at work and I want to thank our team for

their dedication and diligence in getting

Karma back on track. The local commu-

nities, suppliers, and the government,

have been extremely supportive of the

return to work.”

Karma has been designed as an

open-pit, heap leach project which will

produce 97 000 oz/a of gold (average)

over an 8,5-year mine life.