Preventative measures

Clear responsibilities across contractual boundaries – e.g. engineering

company / logic solver vendor / commissioning team

Use same logic solver and software library project after project – enabling

stronger control of FAT, verification and validation procedures

Early code review at FAT

Ensure code review results communicated back to team, and using the

same team again…

Audit vendor’s MOC and commissioning procedures

Export software parameters for offline checking

Neil Wakeling, August 2014