Previous Page  16 / 60 Next Page
Information
Show Menu
Previous Page 16 / 60 Next Page
Page Background

14

MODERN MINING

May 2017

MINING News

Nkuluwisi adds to the potential of New Luika

Shanta Gold, listed on AIM, has provided

an update from its ongoing exploration

programme within, and surrounding, the

New Luika Gold Mine (NLGM), located in

the Lupa goldfield of south-west Tanzania.

In March this year, Shanta released

encouraging drilling results from the

Nkuluwisi mineralised target, located

approximately 12 km north-west of the

NLGM’s central processing hub. Since

March, the company and its indepen-

dent resource consultants have worked

to produce a JORC-compliant Code (2012)

maiden resource for Nkuluwisi.

Total resources declared for Nkuluwisi

amount to 3,97 Mt at 1,1 g/t for 140 894

ounces of gold. The measured resources

total 224 000 t at 1,29 g/t for 9 266 oz of

gold while the indicated resources total

2,3 Mt at 1,13 g/t for 83 888 oz of gold. In

addition, the deposit has inferred resources

of 1,44 Mt at 1,03 g/t for 47 761 oz of gold.

Toby Bradbury, Shanta’s CEO, com-

mented: “The significant scale of Nkuluwisi

opens the door to possible expansion

options at our flagship New Luika Gold

Mine to target lower grade orebodies

which could increase production levels

and add to mine life. The NLGM already

has resources of 9,47 million tonnes at

2,24 g/t for 683 000 oz that sit outside the

recently updated Revised Mine Plan and

the Nkuluwisi maiden resource adds signifi-

cantly to that. Further upside remains along

strike at Nkuluwisi and also at a series of

highly prospective and proximate targets

in the Lupa goldfield identified through our

focused exploration programme.”

Weatherly International, whose shares are

quoted on AIM, reports that its Tschudi

copper project in northern Namibia pro-

duced 3 236 tonnes of copper cathode in

the March quarter. This was 24 % below

nameplate capacity due to slower than

anticipated leach rates for mixed oxide/

sulphide ore stacked in the later months of

2016 and in early 2017. It says that it was

unable to compensate for the shortfall due

to above average seasonal rainfall during

the quarter which prevented short-term

acceleration of mining and stacking.

Mixed oxide/sulphide ore stacked

earlier in 2016 had leached at rates as

predicted in the 2012 Bankable Feasibility

Study (BFS). However mixed ore stacked

later in 2016 showed slower leaching char-

acteristics over time, leading to the current

production shortfalls.

Investigations are continuing with

appropriate external assistance and advice

to determine how site operating param-

eters may be changed to ensure that

optimal conditions for bacterial leaching

of sulphide minerals are maintained in the

heap in order to maximise leach rates and

ultimate overall recoveries of copper from

stacked ore.

The changes currently under investiga-

tion include changes to solution chemistry,

potential for forced aeration of the heap,

modified irrigation strategies, and possible

changes to lift heights.

In the meantime, capital construction

of the stage two heap leach pad area has

commenced to provide additional time

for the leaching of copper from mixed

ore currently under irrigation, and also

for implementation of changed operating

parameters for this ore prior to sealing and

over-stacking.

Groundwater in the open pits had no

adverse effect on mining during the quar-

Slow leaching hits Tschudi’s first quarter production

The Tschudi project is an open-pit, heap

leach, SX/EW copper mine located near

Tsumeb (photo: Weatherly).

ter, with groundwater inflows managed

using the in-pit pumping systems. Detailed

investigations continue into opportunities

to reduce operating costs and produc-

tion delay risks via capital expenditure to

enable removal of groundwater before it

enters the pits.

During April, says Weatherly, rates of

stacking contained copper metal tonnes

onto the heap have improved and the

rate of leaching copper metal tonnes into

solution is expected to improve during the

June quarter. However April’s cathode pro-

duction tonnage will remain weak.

Full financial year production to June

2017, as previously advised byWeatherly, is

now forecast to be 14 500 to 15 000 tonnes.

The poor production result in the March

quarter has caused C1 quarterly operating

costs to increase to US$5 907/t. Full finan-

cial year C1 costs are now forecast to be

US$5 250 to US$5 350 per tonne.