Previous Page  18 / 60 Next Page
Information
Show Menu
Previous Page 18 / 60 Next Page
Page Background

16

MODERN MINING

May 2017

MINING News

In its report on the quarter ended 31 March

2017, Firestone Diamonds plc, the AIM-

quoted diamond company, reports

that commissioning activities at its new

Liqhobong mine in Lesotho are largely

complete and that the final ramp up is

progressing on track

During the reporting period, 639 000

tonnes were treatedwith nameplate capac-

ity continuing to be achieved on numerous

occasions. Some 103 000 carats were recov-

ered at a grade of 16,1 carats per hundred

tonnes (cpht), compared to 58 000 carats at

a grade of 14,1 cpht in the previous quarter.

Over the three months, Firestone

continued to calibrate the processing

plant with scheduled shut downs as part

of the normal commissioning activi-

ties. The modifications implemented

were primarily designed to address the

low carat recoveries experienced in the

previous quarter. While these modifica-

tions impacted on the volume of tonnes

treated, and in turn carats recovered, they

have proven to be effective with the grade

rising to 20,1 cpht at the end of March.

Final ramp-up at Liqhobong on track

The Liqhobong processing plant seen from the south (photo: Firestone).

In addition, the diamonds are being

recovered with less than 1 % measured

diamond damage, which Firestone views

as extremely positive.

The waste stripping is on schedule and

Firestone is in the process of dewatering

the south-eastern side of the main pit to

begin accessing better quality ore later in

the current quarter.

The project maintained its outstanding

health and safety record, having reached 4

million man hours worked without a single

Lost Time Injury (LTI) at the end of March.

During the period, Firestone held two

diamond sales (in February and March)

in Antwerp. All 127 590 carats on offer

were sold and achieved an average price

of US$107 per carat for total proceeds of

US$13,7 million.

“It is pleasing to see that the improve-

ments andmodifications made to the plant

during commissioning have improved

performance,” comments Stuart Brown,

Firestone’s CEO. “During the quarter, we

have seen a steady improvement in the

grade with our daily recovery exceeding

20 cpht at the end of March following the

implemented modifications. 103 000 car-

ats were recovered in the quarter including

31 special stones larger than 10,8 carats

and, post the period, we were delighted to

recover our first plus 100-carat stone.

“The final commissioning phase has

seen the mine achieve nameplate capacity

on numerous occasions which is very posi-

tive, particularly during the rainy season.”

Paradigm to undertake FEED study for Tongo-Tonguma

Further to its announcement on 28 April

2017 that it had entered into a Tribute Mining

Agreement with Octea Mining in relation to

theTongo-Tonguma kimberlitedykediamond

project in Sierra Leone, Stellar Diamonds

reports it has now entered into a contract for

the Front End Engineering and Design (FEED)

study to be conducted for the underground

mine development of the project. South

Africa’s Paradigm Project Management (PPM)

has been appointed to prepare the study.

The project is reported to be one of the

highest dollar per tonne value kimberlites

in Africa and has the potential to be the sec-

ond largest diamond mine in West Africa.

“The FEED is a very important first step in

the mine development process,” comments

Karl Smithson, Chief Executive of AIM-listed

Stellar. “PPM are highly experienced in the

delivery of diamond mine projects and,

together with SRK Consulting, they will refine

all elements of the mine plan as determined

in the PEA to higher levels of confidence in

order to reduce the project delivery risk.

“With over 66 000mof drilling completed

at the project to date, we will undertake

mine plan related drilling to a depth of 75 m

concurrent with the FEED study.

“Once work commences on the FEED,

it is expected to take approximately four

months to deliver (including drilling) and

will mark the onset of the mine devel-

opment programme. I look forward to

updating shareholders on our progress as

we work to transform Stellar into a long

term, high value diamond producer.”