Previous Page  20 / 48 Next Page
Information
Show Menu
Previous Page 20 / 48 Next Page
Page Background

18

CONSTRUCTION WORLD

JULY

2016

Introduction

Geotechnical work in the marine environment

demands creative solutions to complex chal-

lenges. That’s the nature of the game and there

is no one better at it than Franki Africa, which

has developed a reputation throughout Africa

for its innovative and cost-effective solutions.

It is interesting that in both the marine projects

below, one of the common themes is great

teamwork – a perennial Franki skill.

COVER STORY

Project 1: Dormac Quay Wall

The first project is the construction of a

180 m-long, 16 m-high (4 m above water

and 12 m under water) quay wall for marine

engineering company Dormac’s new floating

dock at their marine works facility at their

Bayhead, Belfast Road site in Durban. Ship-

ping is renowned for tight schedules and high

operational costs and this project is subject

to the same pressures in order to meet the

schedules of the future users of the dock.

Franki Africa’s Paul Pearce says that

this has been a complicated, multifaceted

contract. “Although it is one structure, it has

required many highly specialised geotech-

nical skills for a successful outcome,” he says.

One of these skills was specialised jet

grouting using a rig from Franki owner Keller’s

German division. “In fact the co-operation

between Franki and Keller Germany was most

helpful,” says Pearce, “and confirms

the supreme advantage that we have being

part of the Keller network and able to tap

into the best technology and equipment in

our industry.” He adds that the jet grouting

was a highly technical and complicated ope-

ration requiring top-end management, opera-

tors and support. “After a three-week training

and test phase, the jet grout operations

began and, after some initial hiccups with

Franki Cape Town coming to the rescue with

their experience in jet grouting, we were able

to source the faulty parts from Europe and

continue with a productive and successful

operation,” Pearce says.

There have been a few significant chal-

lenges on this job with the first, as expected,

having to work in tidal conditions and being

exposed to the moods of the ocean. The

Franki crew worked around the clock to

accommodate tidal movement and, operating

when they could; they lay down a high-spec

working platform for the piling rigs. “This was

an exacting job to say the least,” says Pearce,

“but when it was complete we were able to

work with the sea being kept at bay and the

biggest risk to our operation allayed.”

The second challenge from a piling

perspective was the positioning and tol-

erance of the piles in relation to the jet grout

columns. “It was critical to get the positioning

spot on to ensure a vertical face to the

quay wall,” Pearce says. “Our works depart-

ment came up with a very innovative idea

in the manufacture of special guides and

frames to assist us in placing the piles in

accordance with the fine tolerances and

this worked perfectly.”

Piling challenge number three – to

increase our piling production rates – was

FRANKI SHOWS ITS

MARINE EXPERTISE

A panoramic view with the South lead-in jetty

being dismantled (on the left), the North lead-

in jetty completely dismantled and existing

piles cut off at low water mark. In the centre

are grid-lines C and D with the capping beams

and decking in progress (done by Haw & Inglis),

and on the right Franki is busy installing

casings on the 15

th

bay on grid-lines A and B.

1 3

2

Quantities on the

Dormac project

230 no. x 900 mm diameter CFA piles

24 m deep; 180 no. x 800 mm diameter

jet grout columns 16 m deep; 180 m

long x 5 m high quay wall capping

beam; 1 500 m x 63 mm diameter

tie bars; 80 000 m³ dredging and excava-

tions; 6 000 m² new dock yard

surface with services.

Pearce says that Franki is concluding

installing the capping beam and are

currently busy hanging the facial panels

on the quay wall. “This has been a chal-

lenging project but we are proud of our

ability to work in marine conditions

– a skill that we have acquired

throughout the company over many

years. Apart from knowledge and expe-

rience, the most important ingredient

for jobs of this nature is teamwork and

we had that in abundance on this job,’

concluded Pearce.

1. Exposed CFA piles and jet grout

in-fill columns.

2. Quay wall face panels around north

mooring pawl position.

3. Overview of site showing dredging and

CFA piling in progress.