Table 7.2 Planned Operational Improvements
Sewer System Master Plan
City of Morgan Hill
PRELIMINARY
Pipeline Improvements
New/Parallel/
Replace
Diameter
Length
(in)
(in)
(ft)
RP‐1
Gravity Main
ROW Along Holiday Dr to Oak Ln
6
Replacement
6
400
RP‐2
Gravity Main Wright Ave
From 230 ft e/o Garden Ave to Del
Monte Ave
6
Replacement
6
550
RP‐3
Gravity Main
Main Ave
Frome 120 ft e/o Hale Ave to 300 ft
e/o Hale Ave
6
Replacement
6
175
RP‐4
Gravity Main Monterey Rd From 3rd to 4th Street
6
Replacement
6
350
RP‐5
Gravity Main
ROW
Right of Way e/o Manor Ct to 450 ft
w/o Monterey Rd and Bisceglia Ave
6
Replacement
6
200
2/16/2017
Type of
Improvement
Alignment
Limits
Improv. No.
Existing
Diameter