City of Morgan Hill
Sanitary Sewer Flow Monitoring and Inflow/Infiltration Study
12-0248 AEG CofMorganHill FM Rpt.docx
Page 45 of 46
Design Storm Response Summary
The 10-year, 24-hour storm event was applied to the synthetic I/I hydrograph components developed
for each flow monitoring site. This method produces the best estimated response to the design storm
events. These results assume full ground saturation and that the peak I/I flows from the design storm
coincide with peak sanitary flows to produce a “worst-case” scenario of peak wet weather flows.
Table 13 summarizes the final results for the design storm on a site-by-site basis.
Table 13. Design Storm I/I Analysis Summary
Metering
Site
Predicted
Peak Dry
Weather
Flow (mgd)
Predicted
Peak I/I
Rate
(mgd)
Predicted
Peak
Flow
(mgd)
Predicted Total
I/I (gallons)
Site 1
0.34
0.75
1.09
285,000
Site 2
0.58
1.42
2.00
451,000
Site 3
0.56
3.13
3.69
1,134,000
Site 4
0.37
1.02
1.39
279,000
Site 5
1.89
5.26
7.15
2,128,000
Site 6
0.67
1.22
1.89
468,000
Site 7
0.38
2.41
2.80
749,000
Site 8
0.29
0.70
0.99
214,000
Site 9
0.25
1.16
1.40
371,000
Site 10
0.24
0.14
0.39
52,000
Harding
4.46
8.74
13.20
4,075,000