Ranked Capital Projects

2016-2020 FINANCIAL PLAN

CLAYTON RECREATION & CULTURE FACILITY

$39,750,000

In consideration of the growth that has occurred in the East Clayton area and the growth

that is expected over the next few years in the West Clayton area, the planning and

concept design of the first phase of a combined Clayton Heights Recreation & Arts

Centre and Library was completed in 2015. Detailed design will be initiated in 2016

based on the approved capital plan. The 2016 contribution to this multi-year project is

$10,000,000.

OPERATING IMPACT: The 2016 – 2020 Financial Plan includes an additional $1,300,000 in

operating costs for ongoing programming at this facility.

CLOVERDALE TWIN ICE SURFACE

$35,000,000

Due to additional demand for ice sports, there is a need for a new twin sheet arena in the

Cloverdale area. The new arena complex will be designed to be efficient and welcoming

as it serves the community and the region for ice hockey, figure skating, public lessons

& skating sessions as well as dry floor summer use. The 2016 contribution to this

multi-year project is $750,000.

OPERATING IMPACT: The 2016 – 2020 Financial Plan includes a net addition of $270,000

in operating costs for the on-going programming at this facility.

CULTURAL CORRIDOR

$300,000

The Cultural Strategic Plan adopted by Council in 2012, and the Surrey Public Art Plan

recommends expanding Surrey’s cultural corridor

,

which is comprised of cultural

opportunities generally following King George Boulevard, from City Centre to South

Surrey. Expansion of art and cultural opportunities along the Cultural Corridor will

engage the artistic community in creating positive destinations for local residents and

visitors.

OPERATING IMPACT: The 2016 – 2020 Financial Plan does not include additional operat-

ing costs as all costs associated with the implementation and monitoring of this pro-

gram are included within the allocated funding.

DISTRICT ENERGY SYSTEM

$13,933,000

Surrey City Energy began delivering services to their first 2 customers in 2015. Expan-

sion of the system commenced in 2015 to service the next 2 projects that are underway.

This expansion consists of temporary natural gas boilers and buried distribution piping

to connect the new projects. Detailed design work is also underway for a permanent nat-

ural gas peaking plant on the future park site at 103 Ave and 133 St.

320