Background Image
Previous Page  22 / 68 Next Page
Information
Show Menu
Previous Page 22 / 68 Next Page
Page Background

20

CONSTRUCTION WORLD

APRIL

2015

PROJECT PROFILE

Logistics

The only way to travel to St Helena is by sea, and a round trip between

Cape Town Harbour, or Walvis Bay and St Helena (weather permitting)

is roughly 20 - 22 days. This makes logistics a key issue for BRSHAP.

Basil Read, the main contractor, set up bonded forwarding facilities

in Walvis Bay and Cape Town to consolidate materials and plant from

all around the world. A temporary jetty in Rupert’s Bay was built to a

depth of five metres with six mooring points to accommodate a modi-

fied ship that was sourced from Thailand – the NP Glory 4.

The ‘roll on roll off’ ship, was modified to carry 1 million litres of

fuel below decks and was fitted with a 13 m high crane that can move

30 ton container loads of material anywhere on deck. With a carrying

capacity of 2 400 tonnes, it has already completed 32 voyages from

Walvis Bay to St Helena and transported over 50 000 tonnes of cargo,

including 10 million litres (pumped ashore via a floating line), explo-

sives, cement, fly ash, admixtures, sand, construction equipment, rein-

forcing steel and other materials needed for the project. The NP Glory

4 is the first ship to ever touch land and offload directly onto St Helena.

Planning is vital due to the long logistical chain and is carried out well

in advance.

Scope demands a variety of skills

The project required a diverse range of expertise in the different disci-

plines of project management, design, blasting, logistics, road and civil

construction, open cast mining, steelwork, crushing, concrete tech-

nology and commercial building.

The project design had to be practical, giving careful consid-

eration to St Helena’s unique geology, logistical challenges,

limited specialists on the island, materials supply and was adapted to

maximise flexibility of resources.

Dry Gut

St Helena’s lack of flat land was a challenge. The airport is being built

on Prosperous Bay Plain which is made up of ravines that the locals

call ‘guts’. In order to create a runway, these guts had to be filled. The

ENDING

ISOLATION

The Basil Read St Helena Airport Project

(BRSHAP) is a design, build, operate and hand

back contract for an international airport in

St Helena. Situated in the South Atlantic Ocean,

St Helena is one of the most remote islands in

the world – 2 000 km from the nearest mainland.

It has with limited infrastructure, no major

construction equipment, few construction

materials, not even sufficient sand and no

harbour – presenting a unique challenge

for Basil Read.

biggest gut – Dry Gut – spans over 400 m on the southern end of the

runway and was filled with over 8-million m³ of blasted andesite and

basaltic igneous rock and soil to the depth of over 100 m. This quan-

tity would fill 20 Mbombela Stadiums to the roof. A total of 503 day

shifts, 439 night shifts, six days a week, with 450 000 truckloads were

used to fill Dry Gut.

In order to achieve compaction, 1,2 million litres of water was

pumped daily from 16 boreholes into four storage dams. The boreholes

were drilled to avoid interference with St Helena’s water supply.

To minimise settlement with the variable quality of the material,

materials management and rockfill processing had to be conducted

with stringent controls. A settlement monitoring system was

installed into Dry Gut fill at several levels to monitor the fill during and

after construction.

A 260 m long and 120 m wide and 30 m deep open channel was

excavated in the adjacent valley to deviate any rainfall water runoff.

Initially, the design called for a 2 m diameter culvert to run through the

fill but the channel required less maintenance and provided additional

620 000 m

3

of quality fill material.

Haul road

A 14 km haul road with up to 15° gradients was constructed along the

side of a mountain between Rupert’s Bay and the airport site. The road

is used to transport heavy equipment and construction materials from

to the airport site. At the end of the contract, the road will be developed

into a public road. This road winds, twists and rises over 500 metres in

the first three kilometres, an engineering and construction challenge

on its own

Airport runway

Cost effectiveness, the mountainous terrain of the island and

the environment were key elements influencing the design of

the airport runway. Concrete was chosen over asphalt in order to mini-

mise future ongoing maintenance.

Manufactured from 27 000 m³ of concrete using a Wirtgen Paver,

the runway is mostly unreinforced, measures 1 950 m long, 45 m wide

ST HELENA’S