Background Image
Previous Page  30 / 68 Next Page
Information
Show Menu
Previous Page 30 / 68 Next Page
Page Background

28

CONSTRUCTION WORLD

APRIL

2015

PROJECTS AND CONTRACTS

The detail design for the rehabilita-

tion and re-alignment of the road,

including upgrades on 11 culverts,

one river bridge and one road-over

rail bridge, as well as the new in-situ culvert

with a fill height of 9,7 m and wall thickness

of 700 mm and the new Elands River bridge

was done by the SANRAL appointed AECOM/

DMV Baeletsi joint venture.

The construction works were scheduled

to start in November 2012, but were delayed

by environmental issues until April 2013.

The construction time allowed for comple-

tion of the project is 30 months. Currently,

after 24 months into the project, work is well

underway and the initial backlog is slowly

but surely diminishing every month.

Construction challenges

The road rehabilitation specification has an

embargo on the use of stop/go systems. The

challenge, therefore, is to keep the traffic

flowing in both directions while the opposite

side of the road is being constructed. The

available road widths at certain places were

such that the traffic had to be accommo-

dated on freshly built bypasses in the middle

of the rainy season.

This, at times, led to crisis management

solutions to enable the free-flow of traffic.

A rapid increase in heavy vehicles contrib-

uted to the traffic accommodation chal-

lenge on this project. The speed limit was

reduced to 60 km/h at work zones assisted

by the placing of removable speed humps.

The absolute minimum road width to use

was found to be 3,3 m and a working space of

1,6 m was required for the adjacent construc-

tion activities, road signs and flag people.

There were, however, instances along the

route where the road had to be constructed

in third-width sections. Fortunately these

were only applicable for about 8 km of

the road. Traffic in these sections were

separated during phase two to run both

sides of the work zone, a situation which

required extra care and effort from the

contractor’s personnel.

Another aspect that had to be intro-

duced was the construction of temporary

seals during the winter period to allow for

the traffic to be transferred to the newly reha-

bilitated road, as existing old road sections

were deteriorating very quickly and became

unsafe and uneconomical to repair.

Winter seals have been an aspect of

investigation and research by SANRAL and

other entities like the bitumen manufac-

turers and consultant/contractor companies

to try and overcome the big loss in produc-

tion during the embargo period for sealwork

in South Africa (May to September). On the

basis of these research findings, temporary

sealwork was allowed with the use of a speci-

fied bitumen emulsion [SC E1(t)] with 9,5 mm

pre-coated stone, covered by a well designed

slurry mix. Using this design the safe flow of

the traffic as well as the construction produc-

tion could be successfully maintained.

The cuttings in the new alignment

section were done by blasting up to the

required levels. Traffic along the N5 was

re-routed through QwaQwa and for the

remaining traffic on the N5 the time lost due

to waiting for the blasting and clearance of

debris was never more than one hour.

Some sub-surface drainage challenges

were encountered between km 20 and 25.

After an on-site investigation, it was found

that due to the high water table in this area,

several natural springs existed in the road

prism. This problem was solved using a

herringbone system of sub-soil drains.

The Elands River tributary culvert was

done in 11 stages. The floor of the culvert was

completed in total to allow for the collapsible

internal shutter to be pushed along rails to

the adjacent section. The shutter was then

erected again only once the previous section

had been cured.

A total of 120 cub.m of concrete was

cast for the walls and deck of each of the 11

sections. Proper care had to be taken with

the fill adjacent and on top of the culvert.

The final fill reached a height of 9,7 m above

the top of the deck of the culvert. This implies

a static load of 20 ton/m

2

of the culvert deck

slab. The total static weight of material on

the deck slab range in the order of 17 600 t.

The new main Elands River Bridge has

five spans, each consisting of 10 precast

concrete beams. These beams are covered by

an in-situ deck slab of 250 mm, with perma-

nent precast shutters between all beams.

The two abutments are supported by 4 piles

each, which on average have been founded

to a depth of 19 m, while piers 1 and 4 each

have five piles in the order of 9 m deep. Piers

CHALLENGING ASPECTS

of N5 rehabilitation

Werner Venter, contracts engineer

from the DMV/AECOM JV.

Edgar Dube, project manager

from SANRAL.

>

I

I