Background Image
Previous Page  31 / 68 Next Page
Information
Show Menu
Previous Page 31 / 68 Next Page
Page Background

29

CONSTRUCTION WORLD

APRIL

2015

PROJECTS AND CONTRACTS

2 and 3, either side of the river, were founded

on insitu rock.

One interesting fact about the beams

is that no curvature or pre-stressing was

designed for, but rather reinforcing steel in

tension and compression. The lifting of the

beams was approached with some appre-

hension by the contractor, but no sagging or

positioning problems were encountered.

Some challenges were encountered

with the quality assurance testing on the

piles. One instance was discovered where

an anomaly was found on the outside of the

pile. This problem was not initially identified

by the cross-hole sonic logging test between

two opposite tubes, which are situated inside

the rebar cage. This anomaly was discovered

when the pile was opened up prior to the

construction of the pile cap.

Conclusion

This project is one of the first of this magni-

tude whereby no stop/gos were allowed,

unless where existing structures prohibits

the adding of road width to sustain two

way traffic.

The design and construction supervi-

sion by the joint venture of AECOM/DMV

PROJECT TEAM

• Client:

SANRAL

• Consultant:

AECOM/DMV Baeletsi JV

• Contractor:

Raubex Construction

MAIN, LEFT:

Base construction in progress

& RIGHT:

Sub-base stabilisation in progress.

Baeletsi (the latter company has offices in

Harrismith) submitted a comprehensive

design and supervision strategy and have an

equal number of personnel on site during the

supervision phase. The site supervision team

has also been assisted by a learner liaison

officer seconded to the project by SANRAL as

well as four students in training.

The project engineer during the design

phase was Gert Fourie of AECOM, while

Werner Venter of DMV Baeletsi is the project

engineer for the construction phase of the

project. The project should be completed by

August 2015.

Backfill in progress at tributary culvert.

Fill completed over tributary culvert area.

Deck slab reinforcing in progress.

Deck slab reinforcing in progress.

I

I