Background Image
Previous Page  40 / 68 Next Page
Information
Show Menu
Previous Page 40 / 68 Next Page
Page Background

38

CONSTRUCTION WORLD

APRIL

2015

CEMENT AND CONCRETE TECHNOLOGY

The MTN Data Centre, Phase II,

which necessitated the addition

of a second floor to MTN’s Data

Centre in Louwlardia Centurion

using Echo prestressed slabs, is an example

of the latter.

Completed in February 2012, Phase I

comprised a ±3 000 m² single-storey struc-

ture which was roofed with Echo prestressed

slabs. Phase II, begun in January 2014,

entails the construction of a second storey

which is being built on the prestressed slab

roof of Phase I. Once again prestressed

hollow-core slabs, in this instance covering

an area ±2 600 m², was used for the roofing.

The main contractor on both phases was

Grinaker-LTA while DSM Consulting Engi-

neers was the engineering consultancy on

the second phase.

Morten Jerg, contracts director of

Grinaker-LTA, says that the benefit of using

precast slabs as opposed to in-situ concrete

is that it speeds up construction times and

causes minimal disruption.

“We have used Echo slabs on many occa-

sions. They enable us to do away with form-

work and propping, not to mention long

curing times, and in some instances, having

to pour concrete in wet weather. We also like

their smooth soffits.”

The prestressed roof slabs used on

both phases were 250 mm deep and

varied between spans of 2,2 m and 11,5 m.

They were designed to carry live loads of

10 kN/m² and dead loads of 2,5 kN/m² and

were mounted on precast inverted T-Beams

measuring 420 mm deep and 630 mm

wide. The design and manufacture of the

beams were outsourced by Echo. Andreas

Rehwinkel of ENCON did the design and

Civilcon handled the manufacturing.

The beams and the slabs were installed

by Echo using 80 and 200 ton cranes. The

former were placed on 6,5 m high reinforced

cast-in-situ concrete columns. Most of the

columns were cast with additional rebar

which protrudes ±1,5 m through the Echo’s

prestressed slab roof. These may be used at

SLABS

and

cell phone technology connect

The 21

st

century has seen South African construction

professionals making increasing use of precast hollow-core

slabs for the construction of multi-storey buildings and for

the extension of existing structures.

>

a later stage as stub columns for supporting

solar panels or other plant on a suspended

steel grid.

After all the slabs had been placed, a

lightweight politerm screed-to-falls, ranging

between 75-400 mm, was installed. It was

covered by a second 40 mm screed to take

a dual layer of water proofing. Once the new

roof was semi-sealed, Grinaker-LTA was able

to remove the screed on the roof of Phase I.

DSM

consulting

engineer,

Mike

Silberman, commented that the new roof

had been designed in close collaboration

with Echo Group engineer, Daniel Petrov,

who he said was extremely helpful in

ensuring the success of the project.

“Due to the amount of services and

penetrations through the new roof, an in-situ

concrete slab had been investigated as an

alternative to the prestressed slab solution.

“However, the amount of propping

required for an in-situ slab and the high

loading on the existing slab precluded

this choice and this is why we opted for

prestressed concrete slabs,” says Silberman.

Echo Group marketing director, Melinda

Esterhuizen, says precast hollow-core

slabs are to the construction industry

what cell phones are to modern commu-

nications – fast, flexible, multi-functional

and cost-effective.

ABOVE:

A workman finishes off one of the column/

beam joints at MNT’s data centre.

BELOW:

Phase II of

MTN’s Centurion data centre takes shape using Echo

prestressed slabs.

ABOVE:

Echo’s prestressed slabs are supported by

concrete columns and precast beams.

BELOW:

Some

of the installed Echo prestressed slabs of Phase II of

the MTN data centre switch roof project.

I