Morgan Hill, California

168

Zucker Systems

Approvals

94% of applicants had their projects approved.

Specific Positive Responses

Questions 16 and 22 had positive responses above 85% for all three functions finding

that all staff was

courteous

(Q16) and aware of and utilize available City information

that is

online

(Q22).

Building

Of the other 18 questions, building had positive responses above 85% for all but three

questions, 4, 13, and 17.

Q4. I

understand

the City’s Development Review and Plan Check processes. They

are straightforward and not unnecessarily cumbersome or complex, 22% negative

responses.

Q13. The

turnaround time

for review and approval or disapproval or my application

was not any longer in Morgan Hill than other cities or counties where I have filed

applications, 25% negative.

Q17. The

conditions of approval

or plan check corrections applied to my project

were reasonable and justified, 19% negative.

Although these three question exceed our 15% negative threshold they are 25% or

less. Overall the data would conclude that customer service by Building is quite good.

Engineering/Public Works

Engineering had many negative responses on 15 of 18 questions, 4 exceeding our

15% negative, 6 exceeding 25% and 5 exceeding 40%. These are some of the worst

scores we have seen in our many studies.

Q4. I

understand

the City’s Development Review and Plan Check processes. They

are straightforward and not unnecessarily cumbersome or complex, 53% negative

responses.

Q9.

Plan checking

is complete and accurate. Additional problems did not surface

later that should have been caught in the initial review, 40% negative.

Q10. Services were completed by the

date promised

, 67 % negative.

Q11. The City’s promised

delivery dates

are reasonable and acceptable, 44%

negative.