Ten Year Network Development Plan 2015 Annex F |
11
Table 2.4:
Considered capacity increment per scenario
Image courtesy of REN Gasodutos
The assessment of the European gas system under Low and High Infrastructure
Scenarios will show different levels of project interaction according to the degree of
development of infrastructure. The assessment of the European gas system under
the PCI Infrastructure Scenario is used separately only within the TYNDP Step to
measure the benefits from a full implementation of the latest PCI list. Its role is to
provide a feedback loop to Regional Groups.
2.6.3 Capacity increment considered in the Economic Analysis
The incremental approach is at the core of the cost-benefit analysis. It is based on
the differences of indicators and monetary values between the scenario »with the
project« and the scenario »without the project«. The inclusion of a capacity incre-
ment associated to an infrastructure project depends on the status of infrastructure
on both sides of a flange. The next table indicates which increment is used in the
Economic Analysis:
CONSIDERED CAPACITY INCREMENT PER SCENARIO
FLANGE A
FLANGE B
INFRASTRUCTURE SCENARIO IN WHICH THE
CAPACITY INCREMENT IS CONSIDERED
EXISTING OR FID
FID
Low and High
Non-FID
High
None
None
NON-FID
Non-FID
High
NON-FID
None
None