Ten Year Network Development Plan 2015 Annex F |

11

Table 2.4:

Considered capacity increment per scenario

Image courtesy of REN Gasodutos

The assessment of the European gas system under Low and High Infrastructure

Scenarios will show different levels of project interaction according to the degree of

development of infrastructure. The assessment of the European gas system under

the PCI Infrastructure Scenario is used separately only within the TYNDP Step to

measure the benefits from a full implementation of the latest PCI list. Its role is to

provide a feedback loop to Regional Groups.

2.6.3 Capacity increment considered in the Economic Analysis

The incremental approach is at the core of the cost-benefit analysis. It is based on

the differences of indicators and monetary values between the scenario »with the

project« and the scenario »without the project«. The inclusion of a capacity incre-

ment associated to an infrastructure project depends on the status of infrastructure

on both sides of a flange. The next table indicates which increment is used in the

Economic Analysis:

CONSIDERED CAPACITY INCREMENT PER SCENARIO

FLANGE A

FLANGE B

INFRASTRUCTURE SCENARIO IN WHICH THE

CAPACITY INCREMENT IS CONSIDERED

EXISTING OR FID

FID

Low and High

Non-FID

High

None

None

NON-FID

Non-FID

High

NON-FID

None

None