Previous Page  36 / 56 Next Page
Information
Show Menu
Previous Page 36 / 56 Next Page
Page Background

34

CONSTRUCTION WORLD

FEBRUARY

2016

PROJECTS AND CONTRACTS

One of these, the basement for

the new Old Mutual building on

the corner of West and Rivonia

streets (opposite the Gautrain

station) turned out to be one of Franki Africa’s

most challenging projects in the area. While

there were several reasons for this, the three

main challenges were the extensive diabase

dyke on the south west side of the site, the

presence of the Gautrain tunnel, which runs

directly under the site and the integration of

the adjoining Sandown Mews development.

The Gautrain necessitated a challenging

approach for the excavation and ‘expected’

rock profile works directly over its tunnel

alignment along the entire Rivonia Road face.

No blasting was permitted in this region and

there were some anxious moments during

the installation of the soldier piles. As it

turned out the soldier piles were installed

deeper than the final excavation level thereby

providing the first signs that rock might not

be present over the Gautrain alignment.

“This proved to be the case,” says Franki

engineer, Paulo Alves, “with numerous bene-

fits accruing to the client with respect to the

management of the risk in this area.”

He adds that even when blasting in

areas not directly over the Gautrain tunnel,

extreme caution had to be exercised. This was

achieved by constant physical monitoring of

all blasting vibrations in the tunnel.

“In terms of the Sandton Mews 3-level

basement, which also had soldier piles and

anchors as a lateral support solution, while

we were able to remove the piles, and did

so, our overall solution had to include the

geotechnical ‘marriage’ of the two sites i.e.

the physical integration of the Sandown

Mews site into the Old Mutual foundations,”

Alves says.

He adds that the third main challenge,

the diabase dyke, has been a perennial

geotechnical issue in the Sandton area.

“The main problem is that it has weathered

so differently to the rest of the site, which

is granite. When the diabase dyke weathers

it forms a much more clayey material, the

bedrock is generally deeper, it retains more

water and has a localised, elevated phreatic

surface. Also its weathering is very hard and

spheroidal,” says Alves.

Franki is the main contractor working

with Zero Azania as the preferred earthworks

specialists and Alves says that although a

geotechnical report had been presented,

Franki’s experience of ground conditions

when it comes to Sandton basement work,

indicated that an extension of the geotech-

nical investigations was required – a decision

which paid off.

“This revealed the diabase dyke in the

south-west corner of the site, situated directly

over the Gautrain tunnel and confirmed the

Sandton granite profile over the remaining

site footprint. Granitic rock on the north-west

corner was detected at 8 m below natural

ground level, where the basement excavation

extends to its deepest point of a total of

22 m. The shallowest point is situated on the

south-east corner where the excavation is

only 14 m deep.

The design comprised 184 soldier piles

of 600Ø drilled to refusal, 12 500 m

2

of gunite

walls, 860 strand anchors of 600 kN and 750 kN

capacity and 920 soil nails / rock-bolts varying

in length from 3 m to 12 m. The total excava-

tion volume was calculated to be 380 000 m

3

,

of which 80 000 m

3

was in hard rock.

Handover

Site access was granted on 20 October 2014

MOST CHALLENGING PROJECT

In recent months, leading geotechnical solutions provider,

Keller’s Franki Africa, has enhanced its reputation with

several history-making basements in the Sandton area.

>

Completion of inner gunite walls over the Gautrain servitude.