Previous Page  42 / 56 Next Page
Information
Show Menu
Previous Page 42 / 56 Next Page
Page Background

40

CONSTRUCTION WORLD

FEBRUARY

2016

One of the trends within the

construction sector relative

to cranage and heavy lifting

is the resurgence of the use

of heavy precast elements

in construction projects.

This, according to Quentin

van Breda, technical

director of Torre Lifting

Solutions and founder of SA

French, will require much

larger tower cranes than

those typically used on a

construction site.

Commenting on the role of tower

cranes on construction sites, Van

Breda says that their use in terms of

material being handled has varied

over the years. “Originally tower cranes were

seen as general materials handling tools.

They handled almost everything that needed

to be lifted and moved, and this included

large skips with concrete. In the past, slabs

were most commonly poured using tower

cranes,” he says.

Fast track projects

This, however, changed as more and more

projects became fast track. “Fast track project

schedules meant that concrete needed

to be placed faster and where the bulk of

concrete being used was for slabs, pumping

became more common place,” Van Breda

says. “This meant that tower cranes were

handling general materials and when it came

to concrete placement the cranes were used

only for the pouring of columns.”

Van Breda says that with this move

towards precast solutions, Torre Lifting

Solutions has seen an increasing number

of enquiries for tower cranes capable of

handling heavy precast elements such as

flooring slabs on new construction projects.

He says it is significant because this type

of lifting requirement doubles the lifting

capacity of the tower crane required.

“In the normal construction environment

everything is equated to cubic metres of

concrete, and the equation for lifting would

then be, say 2,5 t to be lifted at the required

maximum radius of 50, 60 or 70 metres,” Van

Breda explains. “The entire scenario changes

in the case of heavy precast elements as these

could be as heavy as 4 t to 6 t but would still

need to be lifted at the same radii.”

Good for using cranes

This move towards precast elements is a good

one for industry as the utilisation of much

larger cranes will inevitably result in quicker

cycle times on site even when moving other

materials. Van Breda says that this will make

for greater productivity with the subsequent

cost savings in labour and time.

“What is however noticeable is that few

contractors in South Africa own this size tower

crane, with the population in this category

probably no more than10 in the country,” van

Breda says. He says that a standard run-of-

the-mill tower crane used at the top end on

a construction site for traditional materials

handling would be a 200 mt machine, but in

the case of handling heavy precast elements

the bottom end tower crane would need to

be 385 mt.

The Potain MCT 385 is a topless crane

which is easily erected with a mobile crane,

and the load chart is ideal for lifting heavy

precast panels at increased radii, while

providing the construction site with the addi-

tional flexibility and convenience that a tower

brings to a project.

Even though this is a big tower crane, the

individual components never exceed

10 t and this, according to van Breda, ensures

that erection and disassembly fall within the

parameters of normal mobile cranes.

“This is particularly important where

space constraints exist and this is, as all

contractors know, always a factor with urban

construction projects.”

It was designed jointly by Manitowoc

engineers in Europe and Asia to serve several

types of markets, and offers a 2 metre mast

with a maximum free standing height of

64,9 metres. This compact mast, along with a

compact jib design and a streamlined counter

jib, make the tower crane easy to assemble

and transport. “This is a major advantage on

crowded urban projects,” Van Breda says.

Telescoping the crane is made easier

as the hook height can be 50 metres above

the last anchor points, and in addition, the

design allows for internal climbing on high-

rise applications.

With a 20 t maximum capacity, the Potain

MCT 385 is equipped with frequency-con-

trolled mechanisms for hoisting, trolleying

and slewing, facilitating smooth movement

and precise positioning. This is an important

feature when handling and placing such large

precast elements. Van Breda says

that servicing the mechanisms is straightfor-

ward as they are conveniently located and

easily accessible.

“The larger Potain towers will be

supported through the same infrastructure

as all Potain tower cranes, and this includes

technical input and support from the time

of specifying the crane through to erection

by skilled technical teams. Ongoing mainte-

HEAVY PRECAST

elements resurges

>