Previous Page  29 / 60 Next Page
Information
Show Menu
Previous Page 29 / 60 Next Page
Page Background

July 2016

MODERN MINING

27

COAL

Drill rig operating at the Mabesekwa project.

and that the project was being developed

to supply electricity to South Africa in

terms of the cross-border procurement

programme.

The project calls for two or four gen-

erating units, each with an output of

150 MW. It is expected that circulat-

ing fluidised bed boilers will be used.

Due to the fact that Botswana is a water

scarce country, the project would deploy

a dry cooling system.

The water supply strategy includes

the construction of a pipeline from the

Shashe Dam, approximately 60 km from

the project site, which will provide raw

water to the water treatment plant and

other plant and equipment as required.

A nearby wellfield with 18 boreholes

and sufficient capacity will provide a

back-up water supply solution.

A positive coal mining pre-feasibility

study (PFS) by Ukwazi Mining Solutions

to define the mine configuration and

technical and economic potential of the

Mabesekwa coal project was completed

in August 2015.

The coal supplied is expected to have

ash content of less than 30 % and pro-

duce an approximately 17 to 19 MJ/kg

product which will be transported to the

power plant by a conveyor system. The

mine will be a conventional open pit.

Shumba’s second advanced proj-

ect – the Sechaba Coal Independent

Power Producer (SCIPP) project – envis-

ages a 300 MW coal-fired power plant

being developed to supply electric-

ity to Botswana and other countries

in Southern Africa. At this stage

Shumba Energy is the sole developer

but Phumaphi told delegates to the

Gaborone conference that the company

was in discussions with several poten-

tial strategic partners.

Based on the completed conceptual

design study undertaken by Parsons

Brinckerhoff Power, the SCIPP power

plant is envisaged to be configured as

a 2 x 150 MW (gross capacity) coal-

fired facility. The contracted net power

available would be approximately

270 MW after deduction of auxiliary

consumption.

The boiler furnace will be of the cir-

culating fluidised bed subcritical natural

circulation type with one steam genera-

tor provided for each unit, with dry air

cooled condenser technology. Sulphur

Oxide (SOx) control will be achieved by

in-situ SOx capture by limestone dosing

in the boiler furnace. Particulate matter

control will be achieved with electro-

static precipitators.

The estimated in-situ coal resource at

Sechaba is 1,14 billion tonnes, predomi-

nantly contained in two main coal seams

– the upper Taukome Bright Seam (TKS)

and the lower Morupule Main Seam

(MMS). Average seam thicknesses are

2,6 m (TKS) and 3,7 m (MMS) with the

coal found at average depths of 30-100 m.

As with Mabesekwa, Ukwazi has been

responsible for a mining pre-feasibility

study for Sechaba which was completed

in 2014. The selected mine configuration

targets surface and mining infrastructure

and an underground mine to ramp up

to 1,5 Mt/a in the shortest possible time

frame and at the lowest cost. After this

production level has been established, it

is envisaged that a phase two expansion

could increase the annual production to

3 Mt/a. Appropriately detailed mine lay-

outs for the boxcut and the underground

mines for MMS and TBS were prepared

and major equipment sized.

Summing up Shumba’s ‘offering’,

Phumaphi said Botswana and the wider

Southern African region offered few

advanced IPP opportunities, which

placed Shumba – with its two advanced

projects – in a very favourable posi-

tion. He said both projects had excellent

infrastructure access and both enjoyed

strong support from the authorities in

Botswana. He concluded by saying that

Shumba was hoping to be providing an

initial minimum supply of 265 MW to

the grid by 2020.

Photos courtesy of Shumba Energy