Previous Page  19 / 64 Next Page
Information
Show Menu
Previous Page 19 / 64 Next Page
Page Background

17

CONSTRUCTION WORLD

SEPTEMBER

2017

ENVIRONMENT & SUSTAINABILITY

“The mobile transformer will do two things, firstly, it will provide a

temporary supply to the project, to mitigate the risk that Eskom

transmission is delayed with energisation of Helios. Secondly, it will

allow for early grid code testing of Loeriesfontein Wind Farm, which

will ultimately increase the chances of early operations, ahead of the

Commercial Operations Date.

“We have worked very closely with Eskom to supply and operate

the mobile transformer, which is typically used by the Utility

to temporarily connect to substations during maintenance or

unplanned shutdowns to allow continued use of substations. Mobile

transformers are not normally used to connect Wind Farms to the

distribution system,” explained Kevin Foster, Country Construction

Manager for Mainstream Renewable Power.

The Helios substation energisation is on track for 15 August

2017, at which point the Loeriesfontein Wind Farm will be able

to commence with final grid code testing prior to commercial

operations. CONCO is responsible for the electrical component of the

balance of plant works, including the engineering, procurement and

construction of the medium voltage collector system, substation,

overhead line connection and the temporary transformer.

How the transformer fits into the plant

Each wind turbine is connected to a step-up transformer which

boosts the generating output of the wind turbine generator from

690 V to 33 kV. These transformers are located at the base of the

wind turbine. From here the cables throughout the wind farm

bring the 33 kV current from the step up transformers to convene

at the substation where the main transformer is situated. The

main transformer at the substation increases the voltage further

from 33 kV to 132 kV – the voltage required to transfer the

power to Eskom.

The Loeriesfontein and Khobab Wind Farms are part of

the South African Government’s Round 3 Renewable Energy

Independent Power Producer Procurement Programme (REIPPP)

and are managed both in terms of construction and operations by

Mainstream Renewable Power South Africa. The Loeriesfontein

and Khobab Wind Farms, are expected to be operational by

December 2017.

LWF connects mobile transformer

Loeriesfontein Wind Farm, in the Northern Cape, has been

making use of a mobile transformer to allow for an early

connection to the grid for commissioning of the turbines,

prior to the energisation of the Helios substation, which is

the permanent grid connection.