Previous Page  23 / 64 Next Page
Information
Show Menu
Previous Page 23 / 64 Next Page
Page Background

21

CONSTRUCTION WORLD

SEPTEMBER

2017

Installation of Franki Piles.

“The varying ground conditions with old

rock-filled docks and piers and the high-

water table as described above present a

significant challenge.”

Some of the existing live services which

required special attention to maintain

supply to neighbours.

is effected rapidly using the ‘Down The Hole Hammer’ (DTH)

percussion drilling technique. As with CFA, noise levels are low

and vibration limited. Schultz says that the foundation piles were

designed with flexibility in mind to meet the varying and sometimes

unpredictable ground conditions. Three pile types were used: the

Franki Driven Cast-in-Situ piles, Temporary Cased Augers and

Oscillator piles with individual load bearing capacities from 2 300 kN

to 10 000 kN.

To say that the Franki Pile is the most well-known

piling system in southern Africa is certainly no

exaggeration. Developed circa 70 years ago it is still

one of the most popular pile types in this region. Its

main feature is the large base formed at the toe of

the pile and, in forming it, the end-bearing area is

considerably increased.

It is generally a very economical system, has an

extensive range of pile sizes and, like the other piling

systems used on The Yacht Club site, its noise levels are

relatively low.

Another significant challenge on this project was

the very demanding schedule. “This meant that the

works not only had to be very carefully planned but also

executed to perfection,” says Schultz.

He explains that AMDEC required a phased handover

to the main building contractor so that the critical-

path tower cores and basement sections could be

started whilst Franki were still busy on site. “We started

operations during the latter half of 2016 and completed

everything on time and within budget by mid-March

2017,” he says.

Schultz paid tribute to Franki’s client, AMDEC, and to

bulk earthworks contractor, Ross Demolition. “To have

successfully completed this project on time we needed

it to run like clockwork. This was facilitated by these two

professional companies which pulled out all the stops to

ensure that we could do it,” Schultz concluded.