Previous Page  52 / 64 Next Page
Information
Show Menu
Previous Page 52 / 64 Next Page
Page Background

CONSTRUCTION WORLD

SEPTEMBER

2017

50

ALTERNATIVE POWER

Craig Bouwer, projects and product

manager at Zest WEG Group’s Generator

Sets Division spoke to Construction World

and explained why it is essential to ensure

that this alternative power solution is fit for

the purpose intended.

“While generator sets do not specifically

offer energy consumption reductions,

through careful selection of the major

components such as the engine and

alternator it is possible to reduce diesel

consumption and subsequently the

operating cost of these machines,”

Bouwer says.

Historically, commercial properties have

tended towards a single large generator set

which, according to Bouwer, is not always

ideal. He says that, while it is common

practice to install such a unit to supply the

necessary back up power in the event of a

power outage, there are numerous benefits

to be received by installing multiple smaller

synchronised generator sets in parallel.

Benefits

Firstly, it is more efficient to run smaller

generator sets at full load than one large

generator set at half load. This eliminates

the burning of unnecessary fuel as well as

possible damage to the generator set.

“Not only does this improve fuel economy,

it also reduces the capital outlay for a

commercial property, and most importantly

it will facilitate operational flexibility,”

he says.

This local manufacturer of generator sets

offers standard off-the-shelf units as well as

purpose engineered solutions, and Bouwer

is quick to point out that it is advantageous

for the company’s technical team to be

involved from early on in a project to allow

for the most practical and cost effective

solution to be applied.

Multiple smaller synchronised generators

sets with synchronised controllers

communicate with each other, allowing

optimisation of the load demand. System

reliability and generator set availability is

also improved when installing more than

one set in parallel onto a common bus. This

means that should the first generator set not

start, for any reason, the remaining units will

then provide the power required.

“Zest WEG Group Generator Sets Division

can assist contractors, consultants and

architects at the design stage of a project

to ensure the system can be engineered

to shed less critical load and supply all

essential load from the remaining available

generator sets,” he explains.

FIT-FOR-PURPOSE

power

solutions for commercial buildings

Generator sets have long been accepted in the built environment as a

reliable and constant means of power generation, either as the prime

source of power for continuous operation or as standby to the utility.

This mitigates against a total power outage

situation as would have been experienced if

the system was designed with only a single

large generator.

This type of power solution with

synchronised generator sets facilitates

operational flexibility and means that there

will always be an available unit to supply

critical loads in a breakdown or maintenance

scenario. In addition to this, when there is

more than one generator set operating in

parallel partially loading a generator set will

be avoided and the generator management

system will ensure that only the required

number of generators is operated under low

load scenarios ensuring the units run at their

optimum designed power rating.

When multiple synchronised generator

sets are installed, it is easy for the end user

to expand the backup power supply should

the on-site load increase as the controls and

parallel switchgear are already in place.

Optimising load demand

Chris Watkins, manager drives & automation

at Zest WEG Group, says that it is possible

to further optimise the load demand by

selecting the correct electric motor and

Variable Speed Drive (VSD) combination for

the application.

A large commercial building could have

anything from 40 to 100 electric motors

operating, for example, the HVAC system,

a fire system, a water treatment plant and

compressors for refrigeration. In such a

scenario, significant cost savings could be

achieved if the motor driven applications

are optimised by using top premium

efficiency motors and VSDs as starting/

control method instead of traditional direct

online starters.

“By doing this, it is possible to achieve

further operational savings and by using

VSDs it is also possible to reduce the size of

the generator set,” Watkins says. “Where this

is not done, in some instances the generator

The Zest WEG Group generator installation at the Promenade Shopping Centre in Mitchells Plain.