set needs to be approximately 40% bigger.”

Recent installations by Zest WEG

Generator Sets Division include six 2 000 kVA

generator sets at the Promenade Shopping

Centre in Mitchells Plain. Installed to provide

a total power back up solution, the system

incorporates a synchronising panel which

controls the medium voltage switching and

load sharing.

Involvement at the design stage saw

the provision of a bespoke generator set

solution to the V&A Waterfront comprising

13 smaller generator sets. These 630 kVA

sets have been installed in the parking areas

and the existing building and allow for the

dropping of a generator if it is not required

during low load periods.

Specialist application requirements

also form part of Zest WEG Generator Sets

Division’s market offering and the com-pany

was responsible for the engineering

of two super silent containerised gener-ators

that were installed on the roof top

of the Christiaan Barnard Memorial

Hospital. These sets synchronise with the

mains supply.

Generators for Silo 3, 4 and 5

Three 450 kVA generators were supplied

to the Silo 3, 4 and 5 Project on the

V&A Waterfront as backup power units.

These units are controlled by a common

synchronising panel and feed three different

change overs/buildings within the Silo

precinct, and this is also a good example

of providing a fit-for-purpose solution for a

large commercial complex.

Zest WEG Generator Sets Division

produces both stationary and mobile

generator set solutions from 10 kVA up

to 3 350 kVA at its well-equipped facility

in Cape Town. Integrated packages

include mechanical and electrical

manufacture and assembly as well as

electronic design incorporating in-house

control panel manufacture.

Included in the marketing offering is the

supply and installation of transformers,

cabling, bulk fuel systems and sound

attenuation with standby generators on

a turnkey basis, together with project

management, installation, commissioning

and maintenance.

The super silent purpose built generator sets

being lifted to the rooftop of the Christiaan

Barnard Memorial Hospital.

The three 450 kVA generator sets for the Silo 3, 4 and 5 Project prior to testing

at the Zest WEG Group Generator Sets facility in Cape Town.

BELOW:

Multiple smaller generator sets were

supplied to the V&A and these were installed in