Mechanical Technology — July 2015
17
⎪
Power transmission, bearings, bushes and seals
⎪
T
wo of Europe’s largest synchro-
nous motors, along with the
highest power-rated medium
voltage (MV) drives ever used
in a reversing roughing mill, have been
commissioned by ABB at Tata Steel’s
Port Talbot hot strip mill in South Wales.
The replacement motors and drives
were the focus of a major £25-million
reversing roughing upgrade – a key part
of the rolling process which transforms
a 23 cm thick slab of red-hot steel into
sheet, less than 3.5 cm thick, before
further reducing it to produce hot rolled
strip. The upgrade aims to significantly
increase steel production while improving
final product quality.
The reversing rougher is a heavy
torque application and as such demands
two ABB 12.5 MW salient pole synchro-
nous motors, together with two ABB
MV drives rated at 36 MVA at 3.1 kV,
to power the slab between a set of rolls.
Previously, two 6.0 MW direct current
(dc) motors, installed in 1985, were
operated some 30% over their intended
capacity. The overload regularly stressed
the windings, making the motors difficult
to maintain and subject to potential
catastrophic failure. Although operating
in overload the roughing mill was still the
bottleneck process for 50% of the time,
putting a hard limit on plant output.
The new synchronous motors give
Europe’s largest motors and drives
power steel roughing mill
ABB has commissioned two of Europe’s largest synchronous motors
and medium voltage drives at the roughing mill at Tata Steel’s hot
strip mill in Port Talbot, South Wales.
Left:
Two of Europe’s largest synchronous motors ever used in a reversing roughing mill have been commissioned by ABB at Tata Steel’s Port Talbot hot strip
mill in South Wales.
Right:
The upgrade aims to increase steel production significantly while improving final product quality.
the response demanded while the
ACS6000 MV drives with their motor
control platform that uses direct torque
control (DTC), provide unrivalled speed
and torque control. As the slab enters the
reversing rougher there is no perceived
speed drop, as happened with the dc mo-
tors. The new motors and drives control
the slab precisely, with no over shoot in
speed. This results in the slab being pro-
cessed much faster and reduces unneces-
sary torque reversals in the mechanical
drive train. The slow control of the dc
motors caused severe torque swings in
the drive train, resulting in fatigue cycling
to the mechanical equipment. This no
longer occurs, resulting in a much quieter
and safer operating environment, with
improved production capacity together
with increased reliability.
“With the old system, the average
cycle time was 95 seconds. Today, it is
80 seconds,” says Steve Winkley, Tata
Steel’s project manager for the roughing
mill project. “When we change direction
of the bar, it’s much faster than ever
before. When we take advantage of the
motors maximum top speed, this will
result in an average production speed
increase of 30 t per hour – that is a
staggering 200 000 t per year. This sig-
nificant increase in production is almost
a side effect of having to replace the dc
machine. We successfully turned what
was a potentially catastrophic situation
with the overloaded dc motors into an
unprecedented success, breaking a series
of ‘all time’ production records.”
For reversing roughing mills, reliability
is paramount. ABB’s extensive experi-
ence of mill applications together with
proven design technology and manufac-
turing know-how combined with thor-
ough quality control and comprehensive
testing throughout the production cycle,
combined to make Tata Steel’s decision
to use the company easier.
Tata Steel meticulously structured
the shutdown of the existing facility;
a process of design, planning and risk
management that began back in 2011.
This risk mitigation strategy lead to some
90% of the installation being completed,
commissioned and tested before the
plant shutdown.
Over a four-week period, starting
in August 2014, the plant completely
closed for what was to be the most
intense upgrade in 25 years. The old
motors and spindles were removed and
the foundation for the new equipment
prepared. The pre-assembled new mo-
tors were then lifted into position at the
same time that the new spindle system
was being installed. The two motors were
connected with the spindle system and
all the pre-installed and
commissioned
services and control equipment was
connected ready to run the new motors.
“It’s fantastic to see the installation
progress to schedule and really justifies
the approach we took on this project with
90% of equipment pre-installed before
shut down,” says Winkley.
“We are really happy with ABB, in
terms of the equipment and the compa-
ny; both performed absolutely brilliantly,”
he concludes.
q