Previous Page  43 / 60 Next Page
Information
Show Menu
Previous Page 43 / 60 Next Page
Page Background

October/November 2016

O

con Brick has supplied clay

stock bricks for the multi-bil-

lion rand mixed-use Central

Square development, in Sandton’s

richest precinct. Shawn Herbst, Site

Agent for Mota-engil Construction

explains that Sandton has grown so

much over the past five years and civil

engineers have faced the challenges

of product storage spae on site and

the limited street widths. This makes

the need for stock delivery scheduling

a critical requirement.

Herbst explains, “With the narrow

roads of Morningside, Sandton, the

developers need to enable as much

traffic flow-through as possible with-

out causing congestion. Large trucks

loadedwith hundreds of brick pallets

needed to be offloaded quickly. Not

only did we have extremely tight

delivery times, limited storage space

as the Central Square development

grew, we had to move 24 000 clay

stock bricks up to the next level of

construction.” “We chose Ocon Brick

because we knew their clay stock

bricks to be of a high quality and

that the Ocon Brick team would be

available even at short notice, as we

micro-managedcrucial product deliv-

ery schedules to meet the restraints

at site. The Ocon Brick team met the

deadlines and delivered at 6am after

being ordered the previous day. It

is that kind of team work that we

sought and received for the Central

Square site.”

Ocon Brick supplied 5 208 000 for

the Central Square residential blocks,

“Construction commenced inDecem-

ber 2015 and is due for completion

mid-2017. With 52% of the project

already complete; there are a further

nine floors to be constructed and

17 000 m² of concrete parking decks

still to be completed,” says Ocon

Brick consultant, Lucas Steyn. “We

are fortunate that due to our large

manufacturing capability we are able

to hold sufficient stock at any given

point in time enabling us to meet

our customer’s specific time-critical

delivery requirements.”

Central Square

Shangase adds that the new Ma-

juba FET College state-of-the-art

college environment has set a new

standard for learning institutions.

The campus comprises a gatehouse,

administration offices, double-storey

blocks of 2 200m² each, an examcen-

tre, resource centre, student centre

and walkways. “Demand for educa-

tion facilities inDundee has increased

drastically over the past few years

with the growth in population and ris-

ing unemployment levels. To address

this imbalance, Majuba FET College

partnered with Endumeni Munici-

pality to establish Dundee campus

at Mpati. As part of the Umzinyathi

Community Education Project, En-

dumeni Municipality donated land to

Majuba FET College at the entrance

of Dundee for the establishment of

Dundee Technology Centre (DTC).

Tjaart van der Walt, Head Architect

of LVDWArchitects, explained that the

soil was particularly rocky.

“We opted for amore conventional

design in an effort to save on costs.

Brick construction with face brick-

work fulfilled all the requirements of

this college infrastructure. The neu-

tral colours of the face brick blended

in well with the surrounding environ-

ment,” explained Van der Walt.

The bricks were laid in a conven-

tional stretcher bond pattern while

the sturdy herringbone pattern was

selected for the pavers. Pattern work

was included in areas of the face brick

façade to express its African context.

T h e b r i c k w o r k i n c l u d e d

infrastructure

Bricks & Paving

combinations of Corobrik’s range

of Nebraska Travertine and Country

Classic Travertine face bricks for

the maintenance free facades, with

Champagne andBurgundy pavers be-

ing used to compliment the buildings

aesthetic and surrounds.

According to Shangase, “The

choice of colours and textures work

particularly well in the environment.

The life-time cost-saving benefits of

the face bricks is just one of themany

attributes that will serve this project

well into the future”.

Musa Shangase