Table of Contents Table of Contents
Previous Page  1204-1205 / 1248 Next Page
Information
Show Menu
Previous Page 1204-1205 / 1248 Next Page
Page Background

Expected Gas Sourcing

Caspian Region, Russia

Comments about the Third-Party Access Regime

The transmission tariff will be regulated according to EU regulations.

Benefits

Main Driver

Regulation SoS

Main Driver Explanation

Enormous development of the national gasification systemand hence increased consumption/demand on the market

Benefit Description

-Security of supply -Diversification of sources -Development of the region (reversible gas pipelines)

Time Schedule

Grant Obtention Date

Delay Since Last TYNDP

Delay Explanation

MER JSC Skopje for the first time submits its projects in the TYNDP. The possibility of delay is due to the interstate procedures and financing.

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Main gas pipeline section Matka-Grachani (border with

Kosovo)

500

16

Total

16

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

04/2009

07/2010

FEED

07/2010

Market Test

Permitting

Supply Contracts

FID

Construction

Commissioning

2022

2022

NDP and PCI Information

Part of NDP

Yes (Work Program of the Government of

R.Macedonia)

NDP Number

N/A

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 599 of 620

Current TYNDP : TYNDP 2017 - Annex A