Interconnection Macedonia-Bulgaria

General Information

Promoter

MER JSC Skopje

Operator

MER JSC Skopje

Host Country

former Yugoslav Republic of

Macedonia

Status

Planned

Website

Publication Approval Status

Approved

Sponsors

Bulgartransgaz

100%

TRA-N-976

Project

Pipeline including CS

Non-FID

Update Date

25/05/2016

Non-Advanced

Description

Main gas pipeline section Hamzali ² Novo Selo (border with Bulgaria). Within this section the following objects and systems are included: -Line part

in length of 25 km with pipe diameter DN 700

·· -Valve stations with nominal diameter DN700, 3 pcs. -Pig Launching-Receiving station DN700, 2

pcs. -Main Measuring station Novo Selo, -System for automatic operating with the technological process for natural gas transport (DCS/SCADA); -

Line for connection with optic fibres; -Power supply system -Cathodic protection system -Security Signaling System and fire signalization working

(operating) pressure p= 40 bars; maximum pressure (projected) pmax = 54 bars minimum pressure pmin = 25 bars -Capacity 326.000 m3/h (76,4

GWh/d)

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Novo Selo (MK) / Samuilova Krepost (BG)

MER JSC Skopje

2021

BGg/BGT

MK

1.0 GWh/d

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 601 of 620

Current TYNDP : TYNDP 2017 - Annex A