Expected Gas Sourcing
Caspian Region, Russia, Gas storage 7Fields and gas storage Haidach
Comments about the Third-Party Access Regime
Not yet submitted
Benefits
Main Driver
Others
Main Driver Explanation
SoS and market demand to the same extent.
Time Schedule
Grant Obtention Date
Delay Since Last TYNDP
Non existent
Delay Explanation
Non existent
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Burghausen-Finsing
1,200
87
Total
87
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
03/2009
05/2009
FEED
08/2009
12/2009
Market Test
10/2011
Permitting
11/2013
02/2016
Supply Contracts
FID
04/2015
Construction
10/2016
12/2017
Commissioning
2017
2017
NDP and PCI Information
Part of NDP
Yes (Netzentwicklungsplan (NEP))
NDP Number
030-02
Currently PCI
No
CBCA Decision
Yes (2014-04-10)
Market Survey
()
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%