Benefits

Main Driver

Others

Main Driver Explanation

The project results from the modelling of National Development Plan (so called 'Netzentwicklungsplan' NEP) 2012, 2013, 2014, 2015 and 2016 in Germany.

Benefit Description

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

07/2015

11/2015

FEED

Market Test

Permitting

04/2016

04/2017

Supply Contracts

FID

Construction

04/2017

12/2019

Commissioning

2019

2019

NDP and PCI Information

Part of NDP

Yes (Netzentwicklungsplan)

NDP Number

036-04

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 84 of 620

Current TYNDP : TYNDP 2017 - Annex A