Pipeline project "Schwandorf-Finsing"

General Information

Promoter

Open Grid Europe GmbH

Operator

Open Grid Europe GmbH

Host Country

Germany

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

Pipeline "Forchheim-Finsing"

Open Grid Europe GmbH

100%

Pipeline "Schwandorf-Forchheim"

Open Grid Europe GmbH

100%

TRA-F-343

Project

Pipeline including CS

FID

Update Date

15/06/2016

Advanced

Description

Construction of a new pipeline in Bavaria from Schwandorf to Finsing (loop) according to the German Network Development Plan

Regulatory Decisions and

similar material conditions

The project is part of the final German NDP 2015 and the draft German NDP 2016

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

Permitting

Supply Contracts

FID

01/2016

Construction

03/2017

12/2018

Commissioning

2018

2018

NDP and PCI Information

Part of NDP

Yes (Netzentwicklungsplan 2015 (German

NDP 2015))

NDP Number

024-04a and 028-04a

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 85 of 620

Current TYNDP : TYNDP 2017 - Annex A