West to East operation of the IP Waidhaus

General Information

Promoter

GRTgaz Deutschland GmbH

Operator

GRTgaz Deutschland GmbH

Host Country

Germany

Status

Planned

Website

Publication Approval Status

Approved

Sponsors

TRA-F-753

Project

Pipeline including CS

FID

Update Date

26/04/2016

Advanced

Description

Extension of the existing compressor and metering station at the interconnection point Waidhaus allowing gas flows from Germany to the Czech

Republic (max. 2,000,000 Nm3/h). Interruptible capacity will be created.

Regulatory Decisions and

similar material conditions

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

Permitting

Supply Contracts

FID

Construction

Commissioning

2018

2018

NDP and PCI Information

Part of NDP

Yes (Netzentwicklungsplan Gas 2015)

NDP Number

304-01

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

Exemption Granted

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%