Benefits
Main Driver
Others
Main Driver Explanation
The planning project was triggered by an obligation arising out of the decree of the Austrian regulatory authority, E-Control related to the Coordinated
Network Development Plan 2016-2025, whereas a reverse flow of the TAG pipeline system shall be assessed by also taking into consideration potential
entry FZK capacity at the IP Ceršak/Murfeld. As a consequence, TAG GmbH also assesses an upgrade of existing entry DZK capacity to entry FZK capacity
at the IP Arnoldstein/Tarvisio and, correspondingly, an upgrade of existing backhaul capacity ´Exit Baumgartenµ to FZK capacity ´Exit Baumgartenµ of TAG
GmbH in its projects variations.
Benefit Description
PCI Details
PCI Benefits
Project concerns investment in reverse flow capacity
General Criteria Fulfilled
No
Specific Criteria Fulfilled
Market Integration, Security of Supply
Specific Criteria Fulfilled Comments
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
FEED
Market Test
Permitting
Supply Contracts
FID
Construction
Commissioning
2018
2018
NDP and PCI Information
Part of NDP
Yes (Coordinated Network Development
Plan 2017-2026)
NDP Number
TAG
2016/03
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%