Comments about the Third-Party Access Regime

The current Spanish system allows Negotiated and Regulated regimes but, for the moment, only regulated storages are granted.

Technical Information (UGS)

Storage Facility

Pinasses

Storage Facility Type

Salt Cavern

Multiple-Cycle

Yes

Working Volume (mcm)

240.00

It will be the first storage in the area which counts with important transport, interconnection and regas facilities. The first

phase of the project (8 cavities) will achieve the mentioned capacity. However it could be increased in the future.

Time Schedule

Grant Obtention Date

30/09/2018

Delay Since Last TYNDP

Two years delay

Delay Explanation

Permitting process

Schedule

Start Date

End Date

Pre-Feasibility

05/2012

Feasibility

07/2012

03/2016

FEED

09/2012

12/2013

Market Test

09/2018

Permitting

06/2012

09/2018

Supply Contracts

FID

03/2019

Construction

03/2019

03/2023

Commissioning

2023

2023

NDP and PCI Information

Part of NDP

No (As of today there is not NPD.

The project was initially included in a

former draft. Afterwards the draft was

amended without including this

underground storage. Nowadays NPD is

under study and we dont know whether

this underground storage will be included

or not.)

NDP Number

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 139 of 620

Current TYNDP : TYNDP 2017 - Annex A