Tallinn LNG

General Information

Promoter

Vopak E.O.S. AS / Vopak

LNG Holdings B.V/ Port of

Tallinn AS

Operator

Vopak / Elering

Host Country

Estonia

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

Vopak / Vopak E.O.S.

75%

Port of Tallinn

25%

LNG-N-962

Project

LNG Terminal

Non-FID

Update Date

10/06/2016

Non-Advanced

Description

Conventional LNG import terminal bunkering, break bulk, on grid and off grid land transportation for improving Baltic as well as Finnish security of

supply and serving commercial customers. The project includes 6x800 m3 pressurized bullets, connection to the existing berth LOA 198 m; depth

m 2x100m3/h truck loading rack and connection to the low pressure natural gas distribution network located about 1 km from terminal site,

covering about 60% of Estonian gas demand. And one to four flat bottom storage tanks with the total LNG storage capacity of 50 000 m3 to 320 000

m3, with second connection to the berth LOA 365m depth

m capable of handling any size LNG carrier on the market, connection to DN711

MOP 54 bar national high pressure grid located about 13 km from the terminal site. Rail shunting tracks are 200m. Current scope is envisaged to

160 000 m3 x80 000 m3 tanks with 4 bcma connection to the national high pressure grid. (grid connection on separate CAPEX).

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Tallinn LNG

Vopak / Elering

2019

LNG_Tk_EE

EE

121.0 GWh/d