Enhancement of Estonia-Latvia interconnection
General Information
Promoter
Elering AS
Operator
Elering AS
Host Country
Estonia
Status
Planned
Website
Project's URLPublication Approval Status
Approved
Sponsors
Karksi metering station
Elering AS
100%
Puiatu Compressor Station
Elering AS
100%
TRA-N-915
Project
Pipeline including CS
Non-FID
Update Date
15/07/2016
Advanced
Description
The project composes of implementation of reverse flow in Karksi metering station in Estonia and of a compressor station in Puiatu, Estonia. The
reverse flow gas measuring station would be erected to the location of the existing measuring station in Karksi. Karksi reverse flow enables the
measuring of gas quantities thru Estonia with the main advantages of reverse flow used after the commissioning of the Balticconnector offshore
pipeline. Karksi reverse flow enables the full use of Inculkalns UGS for all the market participants. Puiatu compressor station enables the
transportation of gas thru Estonia and the Balticconnector offshore pipeline to the Finnish gas market. The current system design does not enable
the full use of the planned offshore pipeline without a compressor station in south of Estonia. Puiatu compressor station is an integral part of the
physical implementations needed for market integration between the Baltics and Finland.
Regulatory Decisions and
similar material conditions
The Regulators of Finland Energiavirasto and Estonia Konkurentsiamet have made a common CBCA decision for the Balticconnector and
Estonia Latvia interconnection project.
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Karksi
Elering AS
2019
EE
LV
105.0 GWh/d
Elering AS
2019
LV
EE
42.0 GWh/d
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 132 of 620
Current TYNDP : TYNDP 2017 - Annex A