Balticconnector
General Information
Promoter
Elering AS
Operator
Elering AS
Host Country
Estonia
Status
Planned
Website
Project's URLPublication Approval Status
Approved
Sponsors
EE Kiili pressure reduction station
Elering AS
100%
EE Kiili-Paldiski pipeline
Elering AS
100%
EE Paldiski metering and Compressor station
Elering AS
100%
FI Inkoo metering and compressor station
Baltic Connector OY
100%
FI Inkoo-Siuntio pipeline
Baltic Connector OY
100%
FI-EE Inkoo-Paldiski Offshore pipeline
Baltic Connector OY
50%
Elering AS
50%
TRA-N-895
Project
Pipeline including CS
Non-FID
Update Date
20/05/2016
Advanced
Description
New bidirectional offshore pipeline Inkoo Paldiski, DN500, 80 bar of 80 km, plus 50 km onshore pipeline in EE Kiili Paldiski pipeline, DN 700, 55 bar
and 20 km onshore pipeline in FI Siuntio Inkoo pipeline, DN500, 80 bar including metering and compressor stations at both ends with a daily
nominal capacity of 7.2 mcm/day. The power of each compressor station is about 10 MW.
Regulatory Decisions and
similar material conditions
The Regulators of Finland Energiavirasto and Estonia Konkurentsiamet have made a common CBCA decision for the Balticconnector and
Estonia Latvia interconnection project.
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Balticonnector / Paldiski (EE)
Elering AS
2019
EE
FI/BAC
79.0 GWh/d
Elering AS
2019
FI/BAC
EE
79.0 GWh/d
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 129 of 620
Current TYNDP : TYNDP 2017 - Annex A